PLN Warns of Lampung Power Crisis
The Jakarta Globe By Rangga Prakoso
State-owned utilities company Perusahaan Listrik Negara (PLN) said on Wednesday that Lampung would face a power supply crisis unless construction began soon on a long-awaited geothermal plant.
“If the construction of the Rajabasa geothermal plant is delayed further, Lampung will suffer from a [power] deficit like in other regions,” Nur Pamudji, president of PLN, said in Jakarta. ”We hope that the construction of this electricity project can start soon.”
PLN has since 2011 sought permits from the Forestry Ministry to build the plant. The Ministry’s approval is necessary because the proposed plant would operate in a protected forest on the slopes of the Rajabasa mountain.
The Ministry said that it has been considering fears that the project would cause pollution and damage the forest.
The rising cost of construction materials has caused the project’s potential price tag to increase, and for Supreme Energy — the developer of the project — the longer the power plant is delayed, the less profitable the project becomes.
If the project becomes too unprofitable, it will be canceled altogether.
“Of course, if there are no indications regarding the [end of the] delay, we will look for an alternative source of electricity,” Nur said. “What is clear is that it would not be from geothermal energy.”
Rida Mulyana, the Energy and Mineral Resources Ministry’s director general for renewable energy, said the project was not likely to have a detrimental impact on the local environment.
“Our hope is that it does not drag on for too long,” she said. “We have done all we can do, including promoting the project [to the local population]. We are now waiting for guidance.”
The project has passed the muster of a feasibility study, and PLN and Supreme Energy have already signed a power purchase agreement.
The plant had initially been scheduled for completion in 2016, and Rida said that four years of construction would be necessary.
The Indonesian government anticipates the demand for electricity to rise by an estimated 9.5 percent per year for the next five years as the economy continues to grow. Capacity has so far been unable to keep up with demand, leading to power shortages across the country.