Indonesian Political, Business & Finance News

PLN to Add 10 MW of Generators to Overcome Power Supply Deficit in Manokwari

| Source: Antara (Indonesian) Translated from Indonesian | Energy
PLN to Add 10 MW of Generators to Overcome Power Supply Deficit in Manokwari
Image: Antara (Indonesian)

PT PLN (Persero) Customer Service Implementation Unit (UP3) Manokwari, West Papua, is preparing a short-term strategy of adding generators with a total capacity of 10 megawatts to overcome the electricity supply deficit for local residents.

Manager of PLN UP3 Manokwari Arbhy Tryudha said in Manokwari on Monday that the electricity supply from PT Conch Cement Indonesia had dropped significantly, from 13 megawatts to 1 megawatt, due to damage at the power plant.

“In the third week of October 2026 we will commission a 5-megawatt generator, and the second unit will arrive in the second week of November 2026,” he said.

He explained that the electricity needed to serve customers in Manokwari and South Manokwari regencies is roughly 37 megawatts, which has so far been supplied by the steam power plant (PLTU) of PT Conch Cement Indonesia.

The problem has led to rolling blackouts, as the available electricity supply cannot yet meet the needs of all PLN customers in the Manokwari and South Manokwari areas.

“We have also coordinated with the regional government so that this issue is addressed promptly and long-term reliability of the electricity supply is maintained,” he said.

Member of the Manokwari Regency Representative Council (DPRK) Patrick Yauw Meyer said a meeting had been held with PLN UP3 Manokwari regarding the electricity supply deficit, which has caused unrest among residents.

The addition of two generators, each with a capacity of 5 megawatts, is expected to improve short-term supply stability while awaiting the completion of substations in the Warmare plains, Prafi and Masni.

“After the meeting with PLN, we will meet with PT Conch Cement Indonesia and at the same time verify the damage to the power plant,” he said.

According to him, the presence of large-scale investment in the Manokwari region should also contribute to development across various sectors, including reliable electricity supply for local communities.

“I believe a cement factory investing in Manokwari should also contribute to every development programme,” Patrick said.

More from 7 September 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/pln-to-add-10-mw-of-generators-to-overcome-power-supply-deficit-in-manokwari-1788789750)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5730291/pln-tambah-mesin-10-mw-atasi-defisit-daya-kelistrikan-di-manokwari), translated from Indonesian
Print