PLN sends recovery teams to remote areas affected by Flores earthquake
Jakarta (ANTARA) - PT PLN (Persero) has sent recovery teams to a number of remote (isolated) areas that suffered fairly severe impacts, including Palue Island in Sikka Regency and Golo Lebo in East Manggarai Regency. Handling of remote areas has become PLN’s focus after the main Flores electricity system was restored.
“After the main Flores generation system was restored, our attention is now focused on the isolated areas that were affected,” said General Manager of PLN’s Generation Main Unit (UIK) Dwipantara Rita Triani in a statement received in Jakarta on Monday.
On Palue Island, located to the north of Flores Island, the community’s electricity supply was previously supported by a 760 kilowatt (kW) solar power plant (PLTS) along with a battery system and 2x150 kW mobile generators. The strong earthquake tremors caused damage to a number of PLTS and battery components, disrupting electricity supply to the community.
Responding to the situation, she said PLN immediately deployed recovery personnel to inspect and repair the affected PLTS, battery system and mobile generators. “For Palue Island, while repairing the damaged PLTS and batteries, we are ensuring the readiness of the generators as a temporary supply so that the community can get electricity back as soon as possible,” said Rita.
She explained that the recovery process on Palue Island presents its own challenges because the location is separated from the Flores mainland. The dispatch of personnel, equipment and generators must be carried out by sea. Nevertheless, these conditions have not dampened PLN’s efforts to accelerate recovery.
“Access to the location is indeed a challenge, but our team continues to move, bringing the necessary personnel and equipment. We want recovery not only to be fast, but also to be carried out with safety as a priority so that the system that returns to operation is truly in a safe condition,” said Rita.
In addition to generation, PLN is currently also focusing on repairing the distribution network on Palue Island that was also affected by the earthquake. Recovery is being carried out in stages according to the condition of the infrastructure on the ground.
Meanwhile, similar efforts are being carried out in Golo Lebo, East Manggarai Regency. PLN continues to repair the 440 kWp solar power plant affected by the earthquake. As of Monday (17/8), two damaged battery systems have been successfully repaired. The batteries will then be connected to the PLTS so that they can store electrical energy and once again supply electricity to the community.
Rita stressed that PLN will continue to deploy the necessary resources until electricity supply in all affected areas is restored. “The PLN team will continue to work until electricity returns and community activities in the affected areas can gradually return to normal,” she said.