PLN Restarts Kaltim-2 Unit 1 Coal-Fired Power Plant to Strengthen Electricity Supply
Balikpapan (ANTARA) — State electricity company PT PLN (Persero) has resumed operations at Kaltim-2 Unit 1, a 100-megawatt (MW) coal-fired power plant, to strengthen electricity supplies to the Kalimantan Interconnection System after completing maintenance.
“Thank God, another power plant has been successfully reconnected to the Kalimantan Interconnection System. This is good news and a positive development in the various recovery efforts we are continuing with our power-plant operating partners,” said Muchamad Chaliq Fadli, general manager of PLN’s East and North Kalimantan Main Distribution Unit (UID Kaltimra), in Balikpapan on Wednesday.
He said the plant, located on the eastern coast of East Kalimantan, was synchronised with the interconnected grid again at 3.08 pm Central Indonesia Time on Tuesday (10 November).
Kaltim-2 Unit 1 had been undergoing scheduled maintenance since 26 October 2026 before returning to operation. The work included inspections and repairs to a number of the plant’s main and supporting equipment.
He said the plant’s return was expected to gradually increase available electricity capacity to support the activities of residents and businesses.
In addition to restoring existing plants, PLN is increasing supply by renting large-scale diesel generator sets in several areas.
Recovery work on electricity infrastructure is also focused on the Senipah gas-fired combined-cycle power plant. It is currently operating at an available capacity of about 36 MW, against an optimal total capacity of 117 MW.
Senipah operations general manager Fajri said the technical team was accelerating engine repairs and sourcing replacement components in cooperation with the manufacturer.
“We are continuing with various stages of the response, from engine maintenance to meeting requirements for replacement components, while prioritising safety and the reliability of the equipment,” Fajri said.
PLN said several other plants in the regional interconnected grid still required intensive attention, including the CFK, Indoeka and Asam Asam coal-fired power plants, as well as the Peaking gas-fired power plant.
PLN management apologised to the public for the inconvenience caused by electricity supplies that had yet to stabilise fully, and said repairs were being expedited in the field.
Source: jawawa.id (https://jawawa.id/newsitem/pln-restarts-kaltim-2-unit-1-coal-fired-power-plant-to-strengthen-electricity-supply-1794408850)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5847611/pln-operasikan-kembali-pltu-kaltim-2-unit-1-perkuat-pasokan-listrik), translated from Indonesian