PLN Records 30 GW Waiting List for Data Centre Electricity Demand
Jakarta (ANTARA) — State electricity company PT PLN (Persero) has recorded a waiting list for data centre electricity demand totalling 30 gigawatts (GW) and is encouraging investment with developers to meet the large-scale power requirement.
PLN President Director Suroso Isnandar said the scale of demand posed both a challenge and an opportunity for electricity infrastructure development, given that the generation capacity in PLN’s current system stood at around 80 GW.
“Now, the data centre waiting list at this moment is 30 gigawatts,” Suroso said at the 2026 National Energy Forum in Jakarta on Wednesday.
He said PLN was ready to supply data centres during their initial development stages, which generally require 100–300 megawatts (MW), using available capacity in the electricity system.
“But once they move to the next stage of development, especially if they reach gigawatt scale, we will have to discuss co-investment. If necessary, the data centre could build its own power plant,” he said.
He said data centre development needed to take efficient use of resources into account, as the industry’s operations required large amounts of electricity and water.
Meanwhile, Indonesian Renewable Energy Society (METI) chairman Norman Ginting said strong demand from data centres offered opportunities to develop renewable energy power plants, particularly to serve industry in Batam and West Java.
“Because renewable energy, particularly solar power, is intermittent, it requires the Green Super Grid to be ready so that the energy can be delivered, including to meet the high demand from data centres,” Norman said.
According to METI presentation materials, data centre electricity demand is projected to reach 32 GW by 2032, with potential investment in the sector of US$15–20 billion, or around Rp274.55 trillion–Rp366.06 trillion, by 2030.
On 27 October 2026, Suroso said data centre electricity demand had reached 20 GW, excluding planned additional generation capacity of 69.5 GW under the 2025–2034 Electricity Supply Business Plan (RUPTL).
PLN is also developing time-based renewable energy certificates (T-RECs) with Princeton Digital Group, as part of the 31st United Nations Climate Change Conference (COP31) in Antalya, Türkiye, in November 2026.
In a related development, Deputy Minister of Communication and Digital Affairs Nezar Patria said on 10 November 2026 that data centre development should be accompanied by stronger electricity networks, greater use of renewable energy, more efficient cooling systems and water management.
Source: jawawa.id (https://jawawa.id/newsitem/pln-records-30-gw-waiting-list-for-data-centre-electricity-demand-1795607657)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5878071/pln-catat-daftar-tunggu-kebutuhan-listrik-pusat-data-capai-30-gw), translated from Indonesian