PLN Ready to Add 700 MW of Generation Capacity to Strengthen Electricity Supply
Makassar (ANTARA) — PLN is ready to add 700 MW of generating capacity in Sulawesi, with operations scheduled to begin in early 2027, as part of efforts to strengthen the reliability of the island’s electricity supply.
“PLN will accelerate the addition of generating capacity to reach 700 megawatts (MW). This will also anticipate growth in electricity demand from the public and businesses,” PT PLN (Persero) President Director Suroso Isnandar said in a statement in Makassar on Wednesday.
The additional capacity is estimated to meet the electricity needs of around 1 million to 1.1 million customers. Supply is also being strengthened through the installation of several diesel power plants (PLTD) in Punagaya, Jeneponto Regency, South Sulawesi.
Suroso said PLN staff were continuing to work at full capacity to optimise supply and speed up the recovery of electricity services. He also apologised to the public for the impact of the current electricity conditions.
“Everyone at PLN is working hard day and night to find solutions so that this issue can be resolved as soon as possible. We apologise for the inconvenience experienced by the public, and ask for your prayers and support so that these efforts run smoothly,” Suroso said.
He explained that the El Niño phenomenon in recent months had reduced water availability in several catchment areas.
This has affected production at a number of hydropower plants, including the Poso, Bakaru and Malea hydropower plants, as well as several mini-hydropower plants. The situation has reduced available electricity supply by around 600 MW.
Meanwhile, Kasman, acting head of the South Sulawesi Provincial Energy and Mineral Resources Office, welcomed PLN’s efforts to optimise supply and accelerate the recovery of the South Sulawesi–Southeast Sulawesi–West Sulawesi (Sulbagsel) electricity system.
He said the regional government fully supported these efforts through stronger cooperation and coordination between agencies.
“The South Sulawesi Provincial Government fully supports PLN’s efforts to maintain a reliable electricity supply. We also encourage all parties to work together to protect the environment and catchment areas as part of efforts to safeguard energy resilience,” Kasman said.
Source: jawawa.id (https://jawawa.id/newsitem/pln-ready-to-add-700-mw-of-generation-capacity-to-strengthen-electricity-supply-1795596891)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5877363/pln-siap-tambah-kapasitas-pembangkit-700-mw-perkuat-kelistrikan), translated from Indonesian