Indonesian Political, Business & Finance News

PLN ready to absorb and distribute 223 thousand MWh of electricity from Bekasi waste

| Source: Antara (Indonesian) Translated from Indonesian | Energy
PLN ready to absorb and distribute 223 thousand MWh of electricity from Bekasi waste
Image: Antara (Indonesian)

PT PLN (Persero) is supporting the government’s initiative to develop Waste-to-Energy Processing (PSEL) by absorbing and distributing 223,584 megawatt hours (MWh) of electricity per year from the Bekasi City PSEL in West Java.

“Electricity demand in Bekasi is quite high. So, we are dedicating the electricity from the Bekasi PSEL to the people of Bekasi. Thus, Bekasi City’s waste comes here (to the PSEL), and the electricity generated is supplied back to Bekasi City,” said PLN President Director Darmawan Prasodjo in an official statement confirmed by ANTARA from Jakarta on Friday.

He explained that his company is preparing the electricity generated by the Bekasi City PSEL to be reused to meet the electricity needs of the region.

In this way, waste processed through the PSEL not only helps reduce environmental problems but also produces energy that can be reused by the local community.

Darmawan stressed that the main objective of building the PSEL is to create a cleaner environment through waste management. Meanwhile, electricity is only one of the products generated from the process.

“So, the main product is not electricity, but the main product is a clean environment. Electricity is merely a by-product of this programme,” said Darmawan.

The Waste-to-Energy Processing facility in Ciketing Udik Urban Village, Bantargebang District, Bekasi City, West Java, is targeted to begin operations in mid-2028 following the groundbreaking by Danantara Indonesia together with Daya Energi Bersih Nusantara on Wednesday (26/8).

Danantara Indonesia Chief Investment Officer Pandu Sjahrir said the Bekasi City PSEL is the second project to enter the construction phase after the Denpasar Raya PSEL, whose construction began in July 2026.

The project is part of efforts to manage urban waste.

The Bekasi City PSEL is designed to process up to 1,500 tonnes of waste per day into clean energy in the form of electricity. The energy generated will be channelled to the PT PLN (Persero) grid.

The project, with an investment value of around Rp3 trillion, is also projected to reduce carbon emissions by around 640 thousand tonnes of CO₂ equivalent per year, reduce the need for final processing site land by around 90 percent, and create around 1,000 green jobs.

From an energy perspective, the Bekasi City PSEL has a net capacity of 27.4 MW. The facility is projected to produce around 223,584 MWh of electricity per year. Assuming an average consumption of household customers with 450 volt ampere power, this amount is equivalent to the electricity needs of around 55 thousand households.

In the project, the electricity generated by the PSEL is purchased by PLN through a Power Purchase Agreement with each PSEL Developer and Operator Business Entity. The electricity purchase price is set at 0.2 US dollars or 20 US cents per kWh for all capacities.

More from 28 August 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/pln-ready-to-absorb-and-distribute-223-thousand-mwh-of-electricity-from-bekasi-waste-1787903609)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5715088/pln-siap-serap-dan-salurkan-223-ribu-mwh-listrik-dari-sampah-bekasi), translated from Indonesian
Print