Indonesian Political, Business & Finance News

PLN installs main and comparison meters at Kubu substation to support new power plants

| Source: Antara (Indonesian) Translated from Indonesian | Energy
PLN installs main and comparison meters at Kubu substation to support new power plants
Image: Antara (Indonesian)

Denpasar (ANTARA) - PT PLN (Persero), through its Bali Distribution Control Unit (UP2D), has strengthened the readiness of the electricity system at the Kubu Substation in Karangasem Regency by installing main kWh meters and comparison kWh meters.

“The installation of main and comparison kWh meters at the Kubu Substation is not only related to energy recording, but also ensures we have accurate data on energy entering and being distributed to the system. This data serves as an important basis for managing and evaluating the electricity system,” said PLN UP2D Bali Manager Petrus Irwan Ichwansaputra in Denpasar on Thursday.

The devices serve to ensure that electrical energy entering the system can be measured and recorded accurately, in line with the increasing number of generation sources connected to Bali’s electricity system.

The installation of the two meters is an important part of ensuring that every unit of energy entering the system can be precisely identified.

He explained that the main meter serves as the reference for energy recording, while the comparison meter provides reference data to check the consistency of measurement results.

However, in a power system, measurement devices are also placed at strategic points, including substations, to determine the amount of energy transferred from one part of the system to another.

According to Petrus, the need for accurate measurement data is increasingly important as the electricity system develops and more energy sources are connected to the grid.

“As the electricity system develops and more energy sources are connected, the quality of measurement data becomes increasingly important. With accurate data, energy management can be carried out in a more measurable, efficient and accountable manner, so that service reliability to the public can be maintained,” Petrus added.

At the Kubu Substation, the presence of main and comparison meters allows PLN to check the consistency of measurement results.

If there are discrepancies in recording, data from both devices can serve as evaluation material for officers to ensure measurement quality is maintained.

Measurement data can also be used to support the energy reconciliation process, evaluate energy flows, and assist decision-making in the operation of the electricity system.

Thus, measurement is not merely about recording figures, but is part of accurate and accountable energy governance.

The installation of main and comparison meters at the Kubu Substation is also part of the system’s readiness to receive and manage energy from new power plants. The presence of new energy sources requires not only readiness of generation, networks and substations, but also a measurement system capable of recording energy accurately.

This is important because every unit of energy entering the system needs to have its quantity and flow identified.

This data serves as one of the bases for PLN in managing system balance, conducting operational evaluations, and ensuring energy can be optimally distributed to customers.

Through the installation of main and comparison kWh meters at the Kubu Substation, PLN UP2D Bali continues to strengthen the quality of energy measurement as part of the readiness of Bali’s electricity system.

More from 20 August 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/pln-installs-main-and-comparison-meters-at-kubu-substation-to-support-new-power-plants-1787244783)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5704201/pln-pasang-meter-utama-dan-pembanding-di-kubu-dukung-pembangkit-baru), translated from Indonesian