PLN Generation Director Checks Control Room to Ensure Reliable Power for Mandalika MotoGP

| | Source: Republika Translated from Indonesian | Energy
PLN Generation Director Checks Control Room to Ensure Reliable Power for Mandalika MotoGP
Image: Republika

Ahead of the main race of the 2026 Mandalika MotoGP on Sunday (11 October 2026), PLN Generation Management Director Rizal Calvary Marimbo inspected the readiness of electricity infrastructure and standby personnel at the circuit and the Sengkol Solar Power Plant in Central Lombok, West Nusa Tenggara. The visit was part of PLN’s efforts to ensure a reliable electricity supply throughout the international motorcycle racing event.

Rizal said preparations for the power supply had been carried out regularly and were now at a crucial stage ahead of the main race. As the climax of the event programme, this stage requires the highest level of readiness. PLN is therefore prepared to maintain the reliability of the generation system and the continuity of supply to supporting infrastructure throughout the event.

“The Mandalika MotoGP is an international event that carries Indonesia’s reputation before the world. PLN has a responsibility to ensure that all activities run smoothly through reliable electricity. We want to check directly that the power infrastructure and standby personnel are ready to provide the best service,” Rizal said.

He said Lombok’s power system currently had 436 megawatts (MW) of available generation capacity to meet residents’ needs and support the operation of various facilities, including the 2026 MotoGP in Mandalika. With peak demand at 324 MW, the system had a reserve margin of 112 MW during the international race.

As an additional layer of protection, PLN has placed standby generators at the Mandalika circuit with a combined capacity of 4,150 kilovolt-amperes (kVA). Peak electricity demand in the area during Saturday’s (10 October) qualifying and sprint race reached 2,930 kVA, up from 2,815 kVA during the same period at last year’s event. PLN said the available supply remained adequate.

Rizal added that monitoring from the electricity control room showed the generators and power supply at the circuit had remained secure during qualifying and the sprint race. Sufficient capacity and operational readiness are important to ensuring the event runs smoothly.

“We have monitored the generators and found them secure, with sufficient power and normal electricity supply at the Mandalika Circuit. Today’s (Saturday’s) qualifying and sprint race also ran normally,” Rizal said.

To strengthen supply reliability, PLN has put 19 uninterruptible power supply (UPS) units, 13 mobile substations and generators with a total capacity of 4 MW on standby. It has also prepared three mobile-substation connection points with capacities of 250 kVA, 400 kVA and 630 kVA, for a combined capacity of 1,280 kVA. The infrastructure is intended to support the deployment of equipment as operational needs arise.

Reliable electricity is important to the smooth running of the 2026 Mandalika MotoGP and to the development of sports tourism in Indonesia. PLN said its infrastructure and supply preparations reflect its commitment to supporting international sporting events and providing a positive experience for riders, organisers and spectators, while strengthening Indonesia’s position as a host of world-class competitions.

More from 11 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/pln-generation-director-checks-control-room-to-ensure-reliable-power-for-mandalika-motogp-1791708661)
Originally published by Republika (https://ekonomi.republika.co.id/berita/tmqh97490/jaga-keandalan-listrik-motogp-mandalika-direktur-pembangkitan-pln-pantau-langsung-control-room), translated from Indonesian
Print