PLN EPI Successfully Conducts Gas-In Commissioning for WNTS Pemping

| Source: Antara (Indonesian) Translated from Indonesian | Energy
PLN EPI Successfully Conducts Gas-In Commissioning for WNTS Pemping
Image: Antara (Indonesian)

Batam (ANTARA) - PT PLN Energi Primer Indonesia (PLN EPI) has successfully and safely conducted the Gas-In Commissioning, or the testing of the West Natuna Transportation System (WNTS) - Pemping undersea pipeline in the Riau Islands (Kepri).

Acting President Director of PLN EPI, Rakhmad Dewanto, stated that the success of the Gas-In Commissioning is a significant step in the execution of the task to construct and operate the WNTS-Pemping pipeline.

“The success of this Gas-und Commissioning is a vital stage in fulfilling the mandate from the Minister of Energy and Mineral Resources (ESDM) to PLN EPI to build and operate the WNTS-Pemping pipeline, so that Natuna gas can be immediately utilised for domestic needs, particularly to support the reliability of the electricity systems in Batam, Central Sumatra, and West Java,” Rakhmad said in a statement received in Batam on Wednesday.

He added that his company is ensuring the readiness of the primary energy supply by closely monitoring every stage of the project until gas can flow to the PLN Batam power plant in Tanjung Uncang.

For information, the gas-in commissioning stage ensures that there are no leaks along the pipeline up to the onshore facilities.

PLN EPI continues to coordinate with all involved parties to ensure that the readiness of the supply and the gas requirements for power plants are aligned with the completion of the infrastructure.

Rakhmad added that the next stage will involve testing the gas flow from the Onshore Receiving Facility (ORF) to the PLN Batam power plant, once the gas allocation from the Government is obtained and commercial documents are finalised.

“Currently, we are discussing gas allocation with the Directorate General of Oil and Gas and SKK Migas, as well as completing commercial documents with both upstream suppliers and buyers, to subsequently allow gas to flow to the power plants,” said Rakhmad.

The Head of the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas), Djoko Siswanto, stated that the success of the hot tapping, construction, and Gas-In Commissioning of the undersea pipeline is not merely a technical achievement, but also a significant milestone in the series of processes bringing Natuna gas through WNTS-Pemping into Indonesia.

“We hope the entire project series can be completed safely, on time, and successfully, so that Natuna gas, which has previously been diverted to Singapore, can be further optimised to meet domestic energy needs,” he said.

For PLN EPI, Djoko noted, this momentum is part of the effort to build a primary energy supply chain that is increasingly reliable, integrated, and based on the optimisation of national energy resources to support energy security and the reliability of Indonesia’s electricity system.

More from 7 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/pln-epi-successfully-conducts-gas-in-commissioning-for-wnts-pemping-1791349116)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5774718/pln-epi-berhasil-laksanakan-pengujian-pengaliran-gas-wnts-pemping), translated from Indonesian
Print