PLN Confirms Purchase of Electricity from Bogor Raya 1 Waste-to-Energy Plant; Rp2.8 Trillion Investment Commences
The central government, through Danantara—managed by PT Danantara Investment Management (DIM) and PT Daya Energi Bersih Nusantara (Denera)—has confirmed the absorption of electricity generated from the Bogor Raya 1 Waste-to-Energy (PSEL) facility. This certainty was marked by the signing of a Power Purchase Agreement (PJBL) with PT PLN (Persero).
The signing of the PJBL took place alongside the inauguration of the Bogor Raya 1 PSEL construction in Galuga, Bogor Regency, West Java, on Thursday (17/0_9). This commercial cooperation provides offtake certainty for the operators and guarantees the project’s operational sustainability throughout the concession period.
“In today’s agenda, Thursday, 17 September 2026, the progress of Bogor Raya 1 PSEL has entered an important stage, namely the signing of the Power Purchase Agreement,” stated the management in an official statement.
This strategic move is part of the commitment to accelerate the clean energy transition and provide sustainable waste management solutions in the Bogor region. This project follows the realisation of similar integrated waste management solutions implemented in Bekasi City and Denpasar Raya two months prior.
In accordance with the mandate of Presidential Regulation (Perpres) Number 109 of 2025, the PJBL is conducted between PLN and the Waste-to-Energy Developer and Operator Business Entity (BUPP). The electricity purchase tariff is set at USD 0.20 per kWh for the entire capacity produced by the facility.
Bogor Raya 1 PSEL is designed with a waste processing capacity of up to 1,500 tonnes per day. The technology utilised is a moving grate incinerator equipped with a multi-layered Air Pollution Control System (APCS) to ensure emissions remain safe.
The project’s environmental standards adhere to international regulations (EU IED). In addition to its environmental impact, the Rp2.8 trillion project is projected to create up to 1,200 jobs. Following its inauguration in September 2026, the facility is targeted to be fully operational by mid-2028.
It was further explained that Bogor Raya 1 PSEL will manage up to 1,500 tonnes of waste per day into electrical energy in the Galuga area and its surroundings. Bogor Raya 1 PSEL becomes the third PSEL facility to enter the construction phase, following PSEL Denpasar Raya (Bali) and PSEL Bekasi City.
Source: jawawa.id (https://jawawa.id/newsitem/pln-confirms-purchase-of-electricity-from-bogor-raya-1-waste-to-energy-plant-rp2-8-trillion-investment-1789664999)
Originally published by Media Indonesia (https://mediaindonesia.com/megapolitan/934579/pln-pastikan-beli-listrik-psel-bogor-raya-1-investasi-rp28-triliun-dimulai), translated from Indonesian