PT PLN (Persero), through its Central Java Development Unit (UIP JBT), has energised the 150 kV substation at the Kendal Special Economic Zone (SEZ), along with the 150 kV Kendal SEZ Incomer overhead transmission line.
The achievement marks a contribution by PLN to the 81st National Electricity Day and underscores its commitment to accelerating power infrastructure development in support of industrial growth and national investment.
The project is particularly notable because the 150 kV Kendal SEZ substation was completed five months ahead of its original target. PLN said this reflected the hard work, coordination and collaboration of its teams and stakeholders, while maintaining safety and construction quality at every stage.
PLN energised two transformers, each with a capacity of 60,000,000 volt-amperes (VA), at the substation. It also completed the 150 kV Kendal SEZ Incomer Line 1, comprising 23 towers along a 16.473-kilometre circuit. The infrastructure is connected to the 150 kV Weleri–Kaliwungu transmission system to strengthen electricity reliability in the area.
Kishartanto Purnomo Putro, General Manager of PLN UIP JBT, said the project’s success was the result of the commitment and joint efforts of everyone involved. He stressed that, despite finishing ahead of schedule, work quality and safety remained priorities.
“Completing the 150 kV Kendal SEZ substation 147 days ahead of target is a special gift from PLN for the 81st National Electricity Day,” Kishartanto said.
He said the achievement depended on the hard work, dedication and close coordination of teams in the field as they addressed construction challenges. PLN continued to ensure that work progressed effectively while prioritising safety and quality, he added.
“For us, accelerating the project is not simply about completing it early; it is also about ensuring that reliable electricity can be provided sooner to support industrial growth and investment,” he said.
Parlindungan, Manager of PLN UPP JBT 4, said completing the project ahead of schedule had presented technical and non-technical challenges. Consistent supervision, stronger coordination and the commitment of personnel to maintaining productivity had enabled the infrastructure to be completed successfully, he said.
“From the outset, we sought to ensure that every stage of construction proceeded according to plan, and even faster, through close coordination with all relevant parties. We addressed challenges in the field together, focusing on solutions, effective implementation and workplace safety. Thanks to the hard work and collaboration of the entire team, the project was completed 147 days early and is ready to serve the electricity needs of the Kendal SEZ,” Parlindungan said.
Jony Oktavian Haryanto, President Director of PT United Power, also welcomed the operation of the 150 kV Kendal SEZ substation. As a business operating in the zone, he said he hoped the infrastructure would strengthen the reliability of electricity supplies and support industrial growth and new investment.
“First, I would like to express my deepest appreciation and thanks to PT PLN (Persero) for bringing the substation in the Kendal SEZ into operation. This is a shared aspiration for businesses, including PT United Power: for electricity supplies in the SEZ to become stronger, better and more reliable,” Jony said.
He said reliable electricity was vital to the continuity of industrial operations, particularly as the Kendal SEZ attracted investment and activity across a growing range of business sectors.
“As we know, electricity is vital to industrial activity. The Kendal SEZ is now attracting substantial investment, with more factories growing and jobs being created, all of which require reliable electricity. We hope this substation will improve the quality and reliability of supply. We also hope our collaboration with PLN will continue to strengthen, bringing more reliable electricity so that further investment comes in, companies can grow and more jobs are created for a better Central Java and a more advanced Indonesia,” he added.
The operation of the 150 kV Kendal SEZ substation is expected to strengthen the electricity infrastructure needed to meet rising energy demand as industrial activity and investment in the zone expand. Reliable power is an important factor in maintaining industrial operations and improving the area’s competitiveness.
The achievement also highlights the importance of cooperation between PLN, its customers and other stakeholders in delivering electricity infrastructure on time, to a high standard and in line with customer needs.