Indonesian Political, Business & Finance News

Pertamina: Indonesia Needs to Import 3m Tons of LNG Per Year by 2025

| Source: The Jakarta Globe

The Jakarta Globe By Tito Summa Siahaan

photo: Workers unload 3-kg canisters of liquefied petroleum gas (LPG) in Semarang on Feb. 26, 2013. (JG/Dhana Kencana)

Jakarta. Indonesia will have to import at least 3 million tons of liquefied natural gas per year by 2025 in order to keep up with domestic demand, according to Salis Aprilian, Pertamina’s senior vice president for gas and power.

“If we have 3 million tons of imported LNG by 2025, then Indonesia will be secure,” Salis said on the sidelines of the Indonesian Petroleum Association conference and exhibition on Friday.

He added that Pertamina had signed a contract to import 0.8 million tons of LNG with US-based Cheniere Energy.

The gas is scheduled to be delivered in either late 2018 or early 2019 under a 20-year contract.

Typically, gas and gas-related contracts are valid for at least 25 years.

Salis said the supply-demand gap for LNG is expected to widen to 3 million tons by 2025 and Pertamina is steadily expanding its capacity to anticipate the trend.

Pertamina plans to purchase two large-scale LNG vessels to help meet growing import needs.

It is currently in the process of converting its LNG plant in Arun, Aceh, to a regasification facility.

The company also plans to build a floating storage regasification unit (FSRU) with a capacity of 1.5 million tons of LNG per annum in East Java in order to anticipate the declining output from the current productive assets in the province.

Salis noted that the initial plan was to build the facility off Central Java’s coast, but Pertamina decided to move locations as the province will see significant improvement in the development of the gas pipeline network.

Typically, FSRU’s are in locations with insufficient gas pipeline networks.

Pertamina announced on Friday that it had begun construction of a 30-kilometer gas pipeline that would connect the FSRU in West Java with state utility firm PLN’s gas-fired power plants and several industrial estates in the province.

The FSRU is operated by Nusantara Regas, a joint venture of Pertamina and state-controlled gas distributor, Perusahaan Gas Negara.

Hendra Jaya, president director of Pertagas, a unit of Pertamina, said the pipeline is expected to cost $65.94 million.

The projects add to the list of Pertamina’s ambitious plans to expand its pipeline network.

Currently the company is in the process of building an 865 kilometer natural gas pipeline.

Pertamina is the country’s state energy company and is one of the almost nine oil and gas companies operating nationwide.

More from 23 May 2014 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/pertamina-indonesia-needs-to-import-3m-tons-of-lng-per-year-by-2025-1400778000)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/business/pertamina-indonesia-needs-import-3m-tons-lng-per-year-2025/)
Print