Permanent Housing for Disaster Survivors in Sumatra Accelerated, 198.92 Hectares of Land Prepared
The construction of permanent housing (huntap) for communities affected by disasters in Aceh, North Sumatra, and West Sumatra is being accelerated through a parallel work scheme. Land preparation, house construction, and the development of infrastructure, facilities, and utilities (PSU) are being carried out simultaneously so that survivors can quickly obtain safe, decent housing that supports their new lives.
To support this target, the Ministry of Housing and Settlement Areas (PKP) has prepared 198.92 hectares of land across 55 locations. The construction covers 6,220 units in Aceh, 919 units in North Sumatra, and 813 units in West Sumatra as the initial phase of a plan to build centralised or communal relocation housing through to 2027.
The acceleration is being achieved by maximising the implementation period of the 2026 fiscal year. Every stage that can be worked on concurrently is being carried out simultaneously so that work is not held up waiting for other processes to be completed.
Expert Staff for Land Affairs, Development Integration and Spatial Planning at the Ministry of PKP, Teddy Paul H. Siagian, said this working pattern is being applied to reduce construction time without neglecting the readiness of each location.
“Here we do it in parallel. So we do not wait for one thing to finish before another begins, but we carry it out simultaneously,” Teddy said in a statement on Monday (24/8/2026).
He made the remarks during the Acceleration Meeting on the Master Plan for the Permanent Recovery Phase Following the Sumatra Disaster on Friday (21/8).
Based on approval from the Financial and Development Supervisory Agency, physical construction may begin once an initial land handover letter from the owner to the regional government is available. Meanwhile, the certification process and resolution of the legal status of the land continues in parallel.
In the field, land clearing work, permanent housing construction, and PSU development are being carried out simultaneously. Components such as doors, windows, and lightweight steel can also be fabricated in advance before being installed on site to shorten construction time.
The construction of supporting infrastructure is also being accelerated through the use of precast components, including U-Ditch for drainage channels. As a result, work on local roads and drainage can proceed immediately once the components are available on site.
Implementation readiness continues to be strengthened through the procurement process. As of 13 August 2026, 48 of 50 construction service packages as well as supervisory consultant or construction management service packages have been published in the procurement process.
The Ministry of PKP is also ensuring that every house built has a clear prospective occupant. Regional governments are being asked to prepare decrees on location determination as well as beneficiary data based on name and address, or by name by address, so that construction genuinely meets the needs of survivors.
“So, for each village, in accordance with the total unit requirement and the land capacity available, we have requested a location determination decree from the regional head. Likewise with the BNBA. So, we are ensuring that the number of units we will build will definitely be occupied by each prospective resident,” Teddy said.