Permanent Housing Construction in North Aceh Accelerated, Land Acquisition Becomes Priority

| Source: detikcom Translated from Indonesian | Infrastructure
Permanent Housing Construction in North Aceh Accelerated, Land Acquisition Becomes Priority
Image: detikcom

The Sumatra Post-Disaster Rehabilitation and Reconstruction Acceleration Task Force (Satgas PRR) has arranged for housing recovery for disaster-affected communities in North Aceh Regency, Aceh, through the construction of 505 permanent housing (huntap) units across seven locations in 2026. This figure is part of a total requirement of 4,827 units with an estimated budget of Rp 1.40 trillion.

Land readiness is a primary concern for accelerating construction, as only one location for 34 units, or 6.7 per cent, has been declared ‘clean and clear’. Meanwhile, 471 units in the other six locations, representing 93.3 per cent, are still in the appraisal stage by Public Accounting Firms (KJPP).

In terms of implementation, Package 1, comprising 415 units valued at Rp 111.66 billion, and Package 2 in Lhok Puuk, consisting of 90 units valued at Rp 24.22 billion, are about to enter the contracting stage. With a 120-day execution period, work is targeted for completion between 9–16 January 2027, extending beyond the 2026 fiscal year.

Consequently, accelerating land acquisition in the six locations has become a key follow-up priority, specifically for the Leubok Pusaka and Lhok Puuk housing sites. Alignment between land readiness and the contracting process is also required to ensure construction can proceed according to the needs of the affected community.

Access to the housing locations is also a concern. Seven bridge projects managed by Kodam Iskandar Muda were at approximately 5 per cent progress and showed no significant development as of 19–22 September 202lag.

Some of these bridges serve as access routes to the Leubok Pusaka and Keudee Sawang housing sites.

“Recovery in North Aceh is ongoing, but the pace is not uniform. Assistance for housing occupancy and stimulants has shown progress, while several bottlenecks still need urgent resolution, particularly land readiness for permanent housing, the distribution of living allowances (jadup), and the recovery of health facilities,” stated the Head of the Aceh 1 Team, Rear Admiral TNI Nouldy J. Tangka, in a written statement on Thursday (24/9/2026).

“Most of these obstacles are administrative and coordinative in nature, and therefore must be resolved immediately so that the community recovery process can proceed more swiftly,” he added.

Housing occupancy assistance has reached 88.32 per cent, covering 7,575 out of 8,577 Beneficiary Families (KPM), while stimulant assistance has reached 72.09 per cent. Meanwhile, the distribution of Living Allowances (Jadup) has only reached 24.20 per cent, or 4,569 out of 18,880 KPM.

There are still 14,311 KPM with requirements of approximately Rp 68.87 billion that need to be addressed urgently.

The recovery of health facilities also requires data alignment and assessment. A total of 21 locations, consisting of 19 Community Health Centres (Puskesmas) and two Auxiliary Health Centres (Pustu), have been allocated Rp 14.21 billion, representing 41.9 per cent of the Aceh allocation.

The Budget Implementation List (DIPA) has been issued, with distribution planned for October–November 2026 and the Handover Certificate (BAST) targeted for December 2026.

Monitoring and evaluation results also revealed discrepancies in the classification of health facility conditions. Of the 18 Pustu previously assessed as only needing cleaning, field results showed that 16 have sustained damage, including five units with heavy damage.

Six Puskesmas were assessed as unaffected, while the dr. Muchtar Hasbi Regional General Hospital (RSUD) has not yet been included in the central government programme.

In the economic sector, the recovery of aquaculture has reached 304.79 hectares, marking the largest aquaculture recovery achievement in Aceh. This is part of the effort to restore the activities of affected communities and support post-disaster livelihood recovery.

Meanwhile, the additional Regional Transfer (TKD) of Rp 31.63 billion, against a plan of Rp 33.63 billion—which includes 92.78 per cent for infrastructure support—has yet to be realised. Accelerating the realisation of TKD is a necessary follow-up to ensure regional recovery support can proceed immediately.

More from 24 September 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/permanent-housing-construction-in-north-aceh-accelerated-land-acquisition-becomes-priority-1790258399)
Originally published by detikcom (https://news.detik.com/berita/d-8677881/pembangunan-huntap-di-aceh-utara-dipercepat-pengadaan-lahan-jadi-prioritas), translated from Indonesian
Print