Pekanbaru Ring Road Toll Project Progress Reaches 77 Percent
PT Hutama Karya Infrastruktur (HKI) has reported that the construction progress of the Pekanbaru Ring Road Toll Project in Riau Province reached 77 per cent by the end of June 2026, with completion scheduled for February 2027.
HKI Corporate Secretary, Resnu Aditya Wuladarman, stated in a briefing received in Pekanbaru on Wednesday that the project’s development is supported by the implementation of several construction technologies that integrate all stages of project execution. The implementation of this technology began during the planning phase through the use of Building Information Modelling (BIM).
“BIM is not only used as a 3D visualisation medium but is applied in an integrated manner from 2D, 3D, 4D, 5D, up to 7D. Through a single interconnected digital model, project information such as engineering drawings, construction stages, costs, and asset data can be managed more effectively, making coordination, design conflict detection, and decision-making faster and more accurate,” said Resnu.
Furthermore, the application of technology in the Pekanlaru Ring Road Toll Project also involves the use of a Common Data Environment (CDE) and Digital Survey, which promotes collaboration and ensures that work control is more effective, transparent, and accountable.
He explained that through the CDE, all documents, working drawings, revisions, and coordination results are managed within a single digital platform that can be accessed in real-time according to authorised access, ensuring the entire team works using the same and most up-to-date data.
Meanwhile, Digital Surveying via drone photogrammetry is used for the rapid, accurate, and documented measurement and verification of embankment work progress. This technology also serves as the basis for volume calculations and the preparation of more objective progress payments.
“The synergy between BIM, CDE, and Digital Survey forms an interconnected digital ecosystem,” he said.
According to him, survey data and field inspections can be used to validate actual conditions against the BIM model, while all supporting documents and information are managed through the CDE so they can be accessed by all stakeholders quickly and in a controlled manner.
Source: jawawa.id (https://jawawa.id/newsitem/pekanbaru-ring-road-toll-project-progress-reaches-77-percent-1783497862)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5640339/hki-progres-pembangunan-proyek-tol-lingkar-pekanbaru-capai-77-persen), translated from Indonesian