Pekanbaru City Government to Pave At-Grade Junction Next Month, Open It in December

| Source: detikcom Translated from Indonesian | Infrastructure
Pekanbaru City Government to Pave At-Grade Junction Next Month, Open It in December
Image: detikcom

Construction of the at-grade junction at the intersection of Jalan Arifin Ahmad and Jalan Jenderal Sudirman, in front of the Purna MTQ complex in Pekanbaru, is being accelerated. The project, which is expected to ease congestion in the area, has entered its final pavement stage, with the base layer being laid.

The Pekanbaru City Government, through its Public Works and Spatial Planning Agency (PUPR), is targeting the junction to be operational in December 2026.

Pekanbaru PUPR Agency head Edward Riansyah said work was proceeding according to schedule. If there are no setbacks, road asphalting will begin next November.

“Work is currently under way. It is on target,” Edward said on Tuesday (27 October 2026).

He said he hoped all stages of the work would proceed smoothly so the junction could open to traffic by the end of the year.

“Hopefully there will be no problems, so we can put it into operation in December,” said Edu, as he is commonly known.

The junction is one of the measures intended to ease traffic congestion where Jalan Jenderal Sudirman meets Jalan Arifin Ahmad. At present, vehicles heading for Jalan Arifin Ahmad have to use the U-turn in front of the Riau Samsat office.

Once the junction is operational, motorists will be able to turn directly towards Jalan Arifin Ahmad without making a U-turn in front of the Riau Samsat office.

The new access arrangement is expected to reduce vehicle queues, particularly at the U-turn in front of the Riau Samsat office and the turning point in front of Koki Sunda, both of which are currently congestion hotspots.

The construction of the Jalan Arifin Ahmad–Jalan Jenderal Sudirman at-grade junction is costing approximately Rp7.6 billion.

The project is being carried out by PT Riau Mas Bersaudara, with supervision by PT Sandi Arifa Consultant. The construction period is set at 180 calendar days.

More from 27 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/pekanbaru-city-government-to-pave-at-grade-junction-next-month-open-it-in-december-1793098403)
Originally published by detikcom (https://news.detik.com/berita/d-8726498/difungsikan-desember-pemko-pekanbaru-aspal-simpang-sebidang-bulan-depan), translated from Indonesian
Print