Padang’s Rp33.75bn Permanent Housing Project Targeted for Completion by End of December

| Source: detikcom Translated from Indonesian | Infrastructure
Padang’s Rp33.75bn Permanent Housing Project Targeted for Completion by End of December
Image: detikcom

Construction of permanent housing for disaster-affected residents in Kampung Sungai, Pauh district, Padang, West Sumatra, is only 9.9% complete. The post-disaster Rehabilitation and Reconstruction Acceleration Task Force (PRR) has called for work to be expedited so the project can meet its target completion date at the end of December 2026.

“Progress on the permanent housing project stands at 9.9%, and the end-December 2026 target requires special attention and acceleration,” Brigadier General of Police Yopie Indra Sepang, head of the PRR Task Force’s monitoring and evaluation team for Padang, said in a written statement on Saturday (7 November 2026).

The housing project, including public infrastructure, facilities and utilities, is being carried out by PT Wahyu Adi Guna through the West Sumatra Housing and Settlement Areas Work Unit. It is funded by the 2026 state budget (APBN), with a contract value of Rp33.75 billion and a 107-calendar-day implementation period starting from the contract date of 16 September 2026.

The PRR Task Force has recommended that the Ministry of Housing and Settlement Areas and the contractor accelerate construction while ensuring that the utilities and beneficiary arrangements are ready. This means completion must focus not only on the houses themselves, but also on preparing the area to support residents’ daily lives.

Alongside housing recovery, the team inspected rehabilitation of the Gunung Nago weir and irrigation network, which were damaged by flooding in November 2025. The disaster in the area also affected 26 houses, one bridge and 390 metres of road.

The rehabilitation is being carried out by the Ministry of Public Works through the Sumatra V River Basin Agency, with PT Adhi Karya (Persero) Tbk as contractor, and is scheduled for completion in 2028. As local residents cannot wait until all work is finished, the PRR Task Force has urged officials to prioritise urgent repairs to restore irrigation and reduce flood risks.

Protecting public access is also a priority through construction of a retaining wall along the Batu Busuk River, funded through regional transfers (TKD). The project is intended to reinforce the riverbank and prevent landslides that could threaten the road. The local government has been asked to oversee quality and speed up the work to maintain safety and keep access open for residents.

“Overall, post-disaster recovery activities are under way, but the permanent housing project needs to be accelerated, urgent infrastructure work prioritised, and coordination and disaster early-warning systems strengthened,” Yopie said.

To support preparedness, the PRR Task Force met the West Sumatra Police Chief to introduce an integrated rapid-reporting application that connects with the public and issues early-warning alerts. The task force and the West Sumatra Police will explore using the system to speed up information-sharing, coordination and initial responses to disasters.

More from 7 November 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/padangs-rp33-75bn-permanent-housing-project-targeted-for-completion-by-end-of-december-1794048663)
Originally published by detikcom (https://news.detik.com/berita/d-8742760/proyek-huntap-rp-33-75-miliar-di-padang-ditarget-tuntas-akhir-desember), translated from Indonesian
Print