Oil and Gas Industry Awaits Outcome of Amendments to Oil and Gas Law
Jakarta, CNBC Indonesia — Research institute ReforMiner Institute said businesses and investors in Indonesia’s upstream oil and gas sector are awaiting the completion and passage of amendments to Law No. 22 of 2001 on Oil and Gas (the Oil and Gas Law).
Legal certainty and regulatory continuity are considered key to attracting new investment and ensuring a favourable business climate in Indonesia.
ReforMiner Institute noted that reforming the regulatory framework by completing the amendments is crucial to providing certainty for the industry. A legal framework is needed to ensure legal certainty, respect for contracts, clarity over the form of the entity responsible for management, and competitive investment arrangements for production-sharing contract contractors (KKKS).
The need for legal certainty is becoming more urgent as a number of upstream oil and gas National Strategic Projects (PSN) enter the physical construction phase in 2026.
Large-scale projects, including development of the Abadi LNG project in the Masela Block, the Northern Hub and IDD projects in East Kalimantan, the South Andaman Gas Hub, and the CCUS facility at Tangguh, are considered to require long-term investment guarantees to ensure construction and development proceed smoothly.
“Stable lifting requires reliable operations, regulatory certainty, faster permits and viable investment economics for mature fields,” ReforMiner Institute said in its report, quoted on Friday (9 October 2026).
Beyond legal certainty at statutory level, upstream oil and gas operations and investment in the field remain hampered by bureaucracy and licensing. Delays in environmental permits (AMDAL and UKL/UPL), permits to use forest areas (IPPKH/PPKH), and uncertainty over the status of Sustainable Food Agricultural Land (LP2B/LSD) frequently create investment bottlenecks.
To remove these technical obstacles, ReforMiner Institute has called for a Presidential Instruction (Inpres) setting a cross-ministerial integrated licensing service-level agreement (SLA) of no more than 30 days.
Faster licensing is expected to go hand in hand with specific fiscal incentives for managing mature fields, such as more flexible production-sharing splits, tax allowances and accelerated depreciation, to preserve the economic viability of enhanced oil recovery (EOR).
ReforMiner Institute stressed that passage of the Oil and Gas Law amendments, licensing certainty and fiscal incentives together are essential to maintaining national oil and gas production amid natural decline rates of 15–20% a year. Without concrete regulatory support and incentives, investment in the upstream sector will be difficult to accelerate to its full potential.
According to data from the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas), average national oil production through 31 July 2026 stood at 578,156 barrels per day (bpd), below the 2026 state budget target of 610,000 bpd.
National gas deliveries reached 5,208 million standard cubic feet per day (MMSCFD), or 94.5% of the 2026 state budget target of 5,508 MMSCFD.
The 2027 state budget sets an oil lifting target of 612,500 bpd, while the target for natural gas lifting is 954,000 barrels of oil equivalent per day (BOEPD).
Government prepares bill’s problem inventory
President Prabowo Subianto has issued a presidential letter appointing government representatives to discuss the Oil and Gas Bill with the House of Representatives (DPR).
One of the ministers appointed to discuss the bill is Energy and Mineral Resources Minister Bahlil Lahadalia.
Following President Prabowo’s instruction, Bahlil said his ministry would form a cross-ministerial team and hold a coordination meeting to prepare the Problem Inventory List (DIM).
“The presidential letter has been signed by the President, and the Energy and Mineral Resources Ministry, as coordinator, will now form a cross-ministerial team. I have issued the letter. We will then hold a meeting to prepare the DIM. The bill was initiated by the DPR, so the executive’s task is to prepare the DIM,” Bahlil said on the sidelines of a blood donation event marking the 81st anniversary of the mining sector at Balai Sudirman in Jakarta on Monday (21 September 2026).
Bahlil said the government could not yet disclose the DIM’s detailed contents because the drafting process was only about to begin. However, he said one area to be strengthened would be the establishment of a Special Business Entity (BUK) for oil and gas.
He said the BUK would be an important instrument for increasing oil and gas lifting, providing business certainty and simplifying licensing for upstream companies.
“The institution will report directly to the President, so that it has greater authority. The technical minister appointed by the President will coordinate technical matters on the President’s instructions,” he said.
President Prabowo has issued a letter to several Cabinet ministers concerning discussions on the Oil and Gas Bill. Letter No. R-45/Pres/09/2026 appoints government representatives to discuss the bill.
The letter was signed by Prabowo on 14 September 2026 and addressed to the Speaker of the DPR.
“With reference to the letter from the Speaker of the House of Representatives of the Republic of Indonesia No. T-10437/LG 01 01/8/2026 dated 18 August 2026 concerning submission of the Bill on Oil and Gas, we hereby assign the Minister of Energy and Mineral Resources, the Minister of Finance, the Minister of Investment and Downstreaming/Head of the Investment Coordinating Board, the Minister of State Secretariat, and the Minister of Law, jointly or individually, to represent the Government in discussions on the bill,” read the letter from Prabowo, received by CNBC Indonesia on Thursday (17 September 2026).
Plans to establish the BUK
A key proposal in discussions on the Oil and Gas Bill is the creation of a Special Business Entity (BUK) to replace the Special Task Force for Upstream Oil and Gas Business Activities (SKK Migas).
DPR Commission XII member Eddy Soeparno said the provision had been proposed in the bill to provide legal certainty. He said the institutional change responds to a Constitutional Court (MK) mandate, after several provisions in the previous law were annulled in 2012.
“This has long been a concern of ours. The Oil and Gas Law revision has long been mandated by the Constitutional Court, which annulled several articles. We therefore believe it is now very important to revise the law,” he told CNBC Indonesia, quoted on Monday (31 August 2026).
The BUK is envisaged as a business entity with authority to manage upstream operations while also acting as regulator. Unlike SKK Migas, the proposed new institution would report directly to the President to shorten bureaucratic processes.
“One of the first things likely to be a focus of attention is the Special Business Entity, or BUK, to replace SKK Migas. The BUK proposed in the bill is a business entity directly accountable to the President,” he said.
Eddy added that the BUK would hold the rights to working areas throughout Indonesia, and that other parties wishing to participate in the upstream sector would have to work with it.
He said the aim was to complete deliberations on the legislation as soon as possible, preferably by October 2026.
Deputy chair of DPR Commission XII Bambang Haryadi said the Oil and Gas Bill offered a long-term solution to bring control and commercial operations in the sector together in accordance with the Constitution.
“The Oil and Gas Bill has been under discussion since 2015. Following the Constitutional Court ruling in late 2012 that dissolved BP Migas because it was deemed contrary to the 1945 Constitution, Presidential Regulation No. 9 of 2013 was issued to fill the legal vacuum temporarily by establishing SKK Migas,” Bambang said.
He said the latest draft’s fundamental difference lay in the state’s full control over all oil and gas business activities.
“The objective is clear: to implement the Constitutional Court ruling. The key point is that control and commercial operations must be under state control. Law No. 22 of 2001 separated control from commercial operations. The Oil and Gas Bill reunites them in accordance with the ruling,” he said.
He said a stronger legal foundation under the new law was expected to improve the upstream investment climate. Certainty over institutional governance was considered key to reviving national oil production.
“That is indeed the objective,” Bambang said when asked whether the bill could increase oil and gas lifting.
Draft provisions of the Oil and Gas Bill
The following are provisions from the draft bill, particularly those concerning the proposed BUK Migas:
Article 5 — Control and commercial operations
Upstream activities referred to in Article 4(3) shall be conducted by the Central Government as the holder of mining authority over oil and gas.
The Central Government, as referred to in paragraph (1), delegates commercial operations in upstream activities to the BUK Migas.
The BUK Migas referred to in paragraph (2) is the holder of oil and gas mining business authority and is accountable to the President.
As holder of oil and gas mining business authority, the BUK Migas shall conduct all commercial operations in upstream activities.
If the commercial operations referred to in paragraph (4) cannot be carried out, the BUK Migas may offer cooperation on a working area to a business entity and/or permanent establishment.
Article 6 — Commercial operations
Oil and gas business activities shall be conducted under business licences issued by the Central Government.
Oil and gas business activities comprise:
upstream activities; and
downstream activities.
The acquisition of business licences for upstream activities referred to in paragraph (2)(a) shall be coordinated and carried out by the BUK Migas.
Upstream activities comprise:
exploration; and
exploitation.
- Downstream activities comprise:
processing;
transport;
storage; and
trading.
BUK Migas: establishment, duties, organs, capital and revenue
Article 63
The BUK Migas referred to in Article 5(2) shall be established under this Law.
The BUK Migas shall manage and control upstream activities.
In carrying out this function, the BUK Migas shall:
conduct operations in working areas in cooperation with contractors under production-sharing contracts, acting as operations manager;
prepare working areas for further development;
select and appoint contractors to operate working areas;
prepare the terms and conditions of production-sharing contracts;
sign production-sharing contracts;
review and submit to the Minister reports on the initial field development plan for production in a working area;
review and approve contractors’ work plans and/or budgets once they have signed production-sharing contracts;
sell the oil and/or gas to which it is entitled under production-sharing contracts;
manage and record revenue generated by upstream activities;
manage and record assets acquired through upstream activities;
record proven oil and gas reserves;
manage upstream activity data;
prepare business plans for oil and gas supply;
invest through participating interests in working areas;
take necessary corporate actions subject to approval by the supervisory board; and
report periodically to the President on upstream operations.
Article 64
- The BUK Migas shall comprise:
a supervisory board; and
a board of directors.
- The supervisory board shall consist of seven people:
one chair, who is also a member; and
six members.
Members of the supervisory board shall be selected by the DPR on the President’s nomination.
The President shall appoint and dismiss the chair and members of the supervisory board.
Article 65
The board of directors shall consist of at least seven people.
The board of directors shall comprise:
a president director;
a deputy president director; and
directors.
- The President shall appoint and dismiss the board of directors.
Article 66
The BUK Migas’s initial capital shall comprise:
state-owned assets used in upstream activities;
state-owned assets held by the Executive Agency for Upstream Oil and Gas Business Activities and SKK Migas; and
working capital sourced from a certain percentage of non-tax state revenue from upstream activities before the BUK Migas is established.
Article 67
The BUK Migas’s revenue shall come from:
proceeds from upstream operations;
income from managing all state-owned assets that belong to the BUK; and
other income from upstream activities.
Article 68
The BUK Migas’s operating budget shall be funded from part of its revenue as referred to in Article 67.
Article 69
Further provisions concerning the BUK Migas, as referred to in Articles 63 to 68, shall be regulated by presidential regulation.
Oil and gas reserves and funds
Article 84
The Central Government, through the BUK Migas, shall plan oil and gas reserves and increase discoveries of reserves for national interests throughout the territory of the Republic of Indonesia.
The Central Government shall establish strategic, buffer and operational oil and gas reserves for national interests throughout Indonesia.
Further provisions on increasing reserve discoveries and establishing strategic, buffer and operational reserves shall be regulated by government regulation.
Article 85
The Minister shall manage oil and gas funds transparently and accountably.
In managing these funds, the Minister shall coordinate with the minister responsible for state finance.
Oil and gas funds shall be sourced from a certain percentage of:
net state revenue from oil and gas;
bonuses to which the BUK Migas is entitled under production-sharing contracts and this Law; and
levies and fees due to the state under applicable laws and regulations.
Oil and gas funds shall be paid into an account in the Minister’s name.
The funds are intended to increase conventional and unconventional oil reserves and gas reserves through exploration, including in open areas, and development…