NTB Parliament Building Budget Could Swell to IDR 250 Billion
The budget for the new West Nusa Tenggara (NTB) Regional House of Representatives (DPRD) building could potentially swell to around IDR 250 billion. This figure comprises approximately IDR 200 billion for construction costs plus a proposed additional IDR 50 billion for interior design and furniture.
Head of the NTB Public Housing and Settlement Areas Agency (PUPRKP), Lalu Kusuma Wijaya, stated that the additional budget was proposed so the new building could be used immediately after the physical construction is completed.
“The initial proposal for the building construction alone was around IDR 200 billion. But there was input to also procure the furniture for the building, estimated at around IDR 50 billion. However, this figure is still a proposal,” Wijaya said when met in Mataram on Tuesday (4/8/2026).
Wijaya explained that the new DPRD building will be constructed with five floors, consisting of one basement for parking and four floors for council members’ workspaces and legislative activities.
The building design incorporates local wisdom representing the three major ethnic groups in NTB: Sasak, Samawa, and Mbojo. The building will also be directed towards implementing a green building concept.
“The Governor has requested the preparation of solar panel usage for electricity and water efficiency. This building will also be integrated with a Public Electric Vehicle Charging Station (SPKLU) on the ground floor to support the electric vehicle era,” he explained.
In addition to being earthquake-resistant, the building for 65 council members will be equipped with underground cable installations, gardens, and a retention pond. The aspiration room will be placed further from the main road to anticipate potential unrest during mass demonstrations.
The project is currently entering the Detail Engineering Design (DED) preparation stage, targeted for completion in September 2026.
“Once the DED is finished, the project will immediately proceed to the procurement phase through an early auction mechanism, which is targeted to start in October or November 2026,” he said.
The construction of the building, funded through the state budget (APBN), will use a single-year contract scheme. The contract signing is targeted for January 2027.
“Physical construction is estimated to take 11 months, so it will be completed by December 2027,” said Wijaya.
If all stages proceed according to plan, the new NTB DPRD building will be handed over and ready for use by early 2028.
“So in 2028 it can be used. The DPRD will no longer be, pardon the expression, they will have returned to their proper place, God willing,” concluded Wijaya.
Source: jawawa.id (https://jawawa.id/newsitem/ntb-parliament-building-budget-could-swell-to-idr-250-billion-1785833499)
Originally published by detikBali (https://www.detik.com/bali/nusra/d-8603858/anggaran-gedung-dprd-ntb-berpotensi-bengkak-jadi-rp-250-miliar), translated from Indonesian