New Toll Road at the Eastern Tip of East Java Ready to Open, Making Bali Feel Within Reach
A number of sections of the Probolinggo-Situbondo-Banyuwangi (Prosiwangi) toll road have finally been completed. Not only that, two sections of the Prosiwangi toll road have already obtained Certificates of Operational Worthiness (SLO).
Citing data from the Toll Road Regulatory Agency (BPJT) on Thursday (13/8/2026), the first is the Gending-Kraksan section spanning 12.88 km. The second is the Kraksaan-Paiton section spanning 11.20 km.
“The Probolinggo-Situbondo-Banyuwangi (Prosiwangi) Toll Road Section 1 and Section 2, spanning 24 kilometres, have been completed and are being prepared for the operational stage,” BPJT wrote.
However, the operation of Sections 1 and 2 must await the results of the Functional and Operational Feasibility Test (ULFO) for the Gending interchange. This interchange will connect the Pasuruan-Probolinggo (Paspro) toll road with the Prosiwangi toll road.
Meanwhile, Section 3, from Paiton to Besuki, has reached 100% construction progress. This toll road section is also still undergoing the ULFO process by BPJT.
With Prosiwangi connected to the toll road network in East Java, travel between areas is expected to become smoother, travel times more efficient — from Probolinggo to Besuki reduced to 1 hour 15 minutes — and logistics distribution towards the eastern part of Java can be further optimised, with travel time to the crossing to Bali becoming faster.
“The presence of the Prosiwangi toll road will improve connectivity in the Tapal Kuda region, facilitate public mobility, and encourage more efficient logistics distribution in East Java,” BPJT wrote.
Source: jawawa.id (https://jawawa.id/newsitem/new-toll-road-at-the-eastern-tip-of-east-java-ready-to-open-making-bali-feel-within-reach-1786600257)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260813105929-4-758846/tol-baru-di-ujung-jawa-timur-ini-siap-dibuka-ke-bali-terasa-sejengkal), translated from Indonesian