New Jakarta-Bandung Toll Road Accelerated, Alternative Route Prepared to Ease Japek Corridor Congestion

| Source: VIVA.co.id Translated from Indonesian | Infrastructure
New Jakarta-Bandung Toll Road Accelerated, Alternative Route Prepared to Ease Japek Corridor Congestion
Image: VIVA.co.id

Congestion on the main Jakarta-Bandung corridor is expected to ease as construction of the Jakarta-Cikampek (Japek) II South toll road continues to show significant progress. The toll section, projected to become an alternative route, has now reached 84 per cent construction progress for Package 2A as of the end of June 2026.

PT Hutama Karya Infrastruktur (HKI), which is part of the WIKA-PP-KMK-HKI consortium, is continuing to accelerate completion of the project so that the operational target can be achieved on schedule.

The Jakarta-Cikampek II South toll road will later serve as an alternative for road users who have relied on the main Jakarta-Cikampek corridor. The new section is expected to improve public mobility while smoothing logistics distribution across Jakarta, West Java and Bandung.

Construction Progress Reaches 84 Per Cent

HKI Corporate Secretary Resnu Aditya Wuladarman said construction of the Jakarta-Cikampek II South toll road Package 2A is being accelerated with a focus on several major works.

As of the end of June 2026, construction progress in the field has reached approximately 84 per cent, indicating that the accelerated completion of the project is proceeding on target.

“At present, HKI is working on a number of major works on the Jakarta-Cikampek II South Toll Road Package 2A Project. One of the major works currently in focus is the concrete rigid pavement works in the mainroad area of Zone 3 and Zone 4,” said Resnu.

Focus on Road Pavement and Toll Structures

In addition to the concrete pavement works, HKI is also preparing a number of structural works that represent important stages before the toll section can be completed.

One of the works with a high degree of difficulty is the installation of girders in an area that directly adjoins the already operational Cimanggis-Cibitung (CCT) toll road.

Because it is located around an active traffic route, the construction process requires intensive coordination with various parties so that the work can proceed safely without disrupting road users.

Four Girder Spans Still Under Way

HKI noted that four girder spans still need to be installed out of a total of 24 spans in the project.

The works comprise:

  • Ramp 1.

  • Ramp 3.

  • Ramp 5.

The highest installation point is at Ramp 1, with a height of approximately 28 metres.

Tags: berita

More from 18 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/new-jakarta-bandung-toll-road-accelerated-alternative-route-prepared-to-ease-japek-corridor-congestion-1784371837)
Originally published by VIVA.co.id (https://www.viva.co.id/berita/nasional/1914511-tol-baru-jakarta-bandung-dikebut-jalur-alternatif-ini-disiapkan-untuk-kurangi-kemacetan-di-koridor-japek), translated from Indonesian
Print