New 69.19 km Toll Road to be Completed by 2027, Shortening Palembang-Jambi Distance

| Source: CNBC Indonesia Translated from Indonesian | Infrastructure
New 69.19 km Toll Road to be Completed by 2027, Shortening Palembang-Jambi Distance
Image: CNBC Indonesia

The Toll Road Authority (BPJT) of the Ministry of Public Works (PU) continues to push for the accelerated completion of the Musi V Bridge, which is a component of the Palembang-Betung Toll Road. This 69.19-kilometre section is a vital part of the development of the Trans-Sumatra Toll Road (JTTS) network in South Sumatra Province.

The Head of BPJT, Ni Komang Rasminiati, stated that the Musi V Bridge structure received its Structural Certificate of Functionality from the Minister of Public Works on 6 July 2026. The completion of this main structure marks a significant milestone in supporting the overall completion of the Palembang-Betung Toll Road.

“This bridge is a specialised structure because it features a total main span of 380 metres, plus approach bridges of 656 metres on the Bengkinang side and 648 metres on the Gandus side, bringing the total bridge length to 1,684 metres,” said Ni Komang, as reported on Saturday (26/9/2026).

To ensure safety and monitor bridge performance, the BPJT is also preparing the installation of a Structural Health Monitoring System (SHMS) equipped with 100 sensor units. This system will be used to continuously monitor the structural health of the bridge.

Overall, the Palembang-Betung Toll Road spans 69.19 kilometres and is divided into three sections. Section 1 and Section 2 are targeted for completion in the fourth quarter of 2026, while Section 3 is expected to be finished in the first quarter of 2027.

The toll road construction initially uses a 2x2 lane configuration, with plans to expand to 2x3 lanes in the final stage. The project represents an investment of approximately Rp14.98 trillion, with construction costs around Rp13.90 trillion and land acquisition costs at approximately Rp390 billion. The toll road concession period is set for 50 years.

The BPJT is also pushing to have the Palembang-Betung section functional during the 2026-2027 Christmas and New Year (Nataru) period. This functionalisation is expected to support smoother public mobility and strengthen connectivity within the South Sumatra region.

The Expert Staff to the Minister of Public Works for Inter-Institutional Relations, Triono Junoasmono, stated that the construction of the Palembang-Betung Toll Road is part of a larger vision to strengthen the Trans-Sumatra Toll Road connectivity, including the potential for the network to extend to Jambi and other parts of Sumatra.

“If we look at the currently operating toll roads, they run from Bakauheni, Lampung, to Palembang. Now, it is continuing with Palembang-Betung, and hopefully, the next phase can enter construction through to Jambi,” explained Trillion.

More from 26 September 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/new-69-19-km-toll-road-to-be-completed-by-2027-shortening-palembang-jambi-distance-1790423525)
Originally published by CNBC Indonesia (https://www.cnbcindonesia.com/news/20260925205911-4-771079/tol-baru-6919-km-ini-rampung-2027-palembang-jambi-terasa-sejengkal), translated from Indonesian
Print