Nagan Raya Access Restored, Economic Activity Begins to Move Again
Access for communities in Beutong Ateuh Banggalang District, Nagan Raya Regency, Aceh, which had been severed by hydrometeorological disasters, is now reconnected. The Post-Disaster Rehabilitation and Reconstruction (PRR) Task Force for Sumatra continues to accelerate repairs to roads, bridges, and river channels.
The restoration of access is expected to strengthen connectivity for residents while reviving economic activity that had been affected by the disaster. Based on monitoring and evaluation by the PRR Task Force on Sunday (9/8/2026), handling is focused on several critical points. These include river channel management and bridge repairs in Blang Puuk Village, as well as addressing landslide material and water overflow covering the Beutong-Celala road section in Beutong Ateuh Banggalang District.
Project Manager for the Genting Gerbang-Jeuram Natural Disaster Handling Project, Feri Ejin, said work in Blang Puuk has shown significant progress. The team has reconstructed the road body that was previously lost due to the disaster while restoring the river flow that had widened and eroded the road back to its original course. Infrastructure protection has also been strengthened through the construction of embankments on both sides spanning 400 metres.
“We are now building embankments on the left and right sides spanning 400 metres. The embankments are being built to protect the main bridge and road construction, so that if a similar event occurs in the future, the road and bridge will be well protected,” Feri said in a written statement on Monday (10/8/2026).
The acceleration efforts still face logistical challenges, particularly the supply of cement and diesel fuel to operate heavy equipment. The work requires at least 400 tonnes of cement in August, while the available supply at the time of monitoring had only reached 45 tonnes. To meet this need, additional supplies are being brought in from Belawan and Dumai. Meanwhile, the fuel requirement for heavy equipment is around 46,000 litres per month.
Despite these obstacles, the field team remains committed to completing work around the river flow near Blang Puuk Bridge through to the Beutong and Celala sections by December 2026.
“We continue to find ways, with the spirit that by December we can complete the project on time,” Feri said.
The restoration of access is already being felt directly by the community. Areas that were previously isolated can now be traversed by vehicles, including large transport vehicles. This has reopened distribution routes for agricultural produce while facilitating the supply of goods from Takengon to Nagan Raya and Meulaboh.
“The community is already being served, so the access that was previously severed has returned. Large cargo vehicles supplying from Takengon to Nagan Raya or to Meulaboh have started coming in,” Feri said.
Head of Administrative Affairs for Commitment-Making Official (PPK) 2.7 Aceh, Fachrun Rizaldi, said contractual work progress has reached 17.29 percent. To accelerate completion, the team is preparing a number of measures, including the addition of nine excavator units and ensuring fuel and cement needs can be met. As access recovers, market activity, plantations, and local SMEs are also beginning to move again.
Representative of the Aceh PRR Task Force Team from the Ministry of Home Affairs, Imran, appreciated the work of the field team, which continues amid challenging terrain and limited material supplies. According to him, one important development is visible in the river flow that had previously widened and has now been successfully redirected to pass beneath the bridge.
“Extraordinary, from a river that was so wide, it can now be concentrated back under the bridge. The progress is remarkable. I know these colleagues work 24 hours. I have passed through here, and even in the afternoon they were still working,” Imran said.
The review in Nagan Raya is part of the PRR Task Force’s comprehensive evaluation of the acceleration of post-disaster rehabilitation and reconstruction in Aceh. In addition to reviewing road and bridge handling in Beutong Ateuh Banggalang, the team also monitored the Gunong Kong Steel Truss Bridge in Alue Wakie Village, Darul Makmur District, which was previously severed and is now awaiting further handling.