MRT Phase 2A Worth Rp25.3 Trillion Targeted for Completion by 2029
PT MRT Jakarta (Perseroda) has stated that the construction cost of Phase 2A of the North-South Line amounts to Rp25.3 trillion, financed through a loan cooperation between the Indonesian and Japanese governments.
“This phase is being built at a cost of approximately Rp25.3 trillion through loan funds from a cooperation between the Indonesian and Japanese governments,” said Corporate Secretary Division Head of PT MRT Jakarta (Perseroda) Rendy Primartantyo in Jakarta on Thursday (13/8).
Phase 2A of the North-South Line will connect Bundaran HI Station to Kota over a distance of approximately 5.8 kilometres and consists of seven underground stations, namely Thamrin, Monas, Harmoni, Sawah Besar, Mangga Besar, Glodok, and Kota.
Phase 2A is divided into two segments: segment one from Bundaran HI to Harmoni, which is targeted for completion by the end of 2027, and segment two from Harmoni to Kota, which is targeted for completion by the end of 2029.
The development progress of Phase 2A of the North-South Line continues to show significant advancement. As of 25 July 2026, construction had reached 62.68% against a target of 61.92%. “For the CP201 contract package, construction has reached 93.90% against a target of 93.89%,” said Rendy.
At Thamrin Station, the construction team has entered the work stage, including the reinstatement of pedestrian areas around the station site, the reconstruction of the Transjakarta integrated bus rapid transit shelter, mechanical, electrical, and plumbing (MEP) installation, as well as roofing and finishing works for entrances 5, 7, and 8.
At Monas Station, the construction team continues to complete interior work and access to entrance 2, the reinstatement of the station box on the north side, as well as the system acceptance test and partial acceptance test stages.
Significant progress has also been made on the CP202 contract package, which covers the construction of tunnels and the Harmoni, Sawah Besar, and Mangga Besar stations, which has now reached 68.00%.
The completion of this contract package, which is one of the civil construction milestones in Indonesia with tunnels and a four-storey underground station, is also being accelerated.
As of July 2026, tunnel boring machine 1 has broken through the south side of Mangga Besar Station, so that the northbound tunnel from Bundaran HI to Kota is now connected.
For the CP203 contract package, progress has reached 86.85%, with work at Kota and Glodok stations, such as pipe installation, cabling, plastering and painting, as well as the installation of ACP wall panels and other architectural works, still ongoing.