MRT Phase 2A tunnel excavation at Mangga Besar completed
Jakarta (ANTARA) - Excavation of the MRT Jakarta Phase 2A tunnel using Tunnel Boring Machine (TBM) 2 under contract package CP202 has been completed after the machine broke through the wall of Mangga Besar Station in Jakarta.
PT MRT Jakarta (Perseroda) Construction Director Weni Maulina said TBM 2 built the southbound tunnel in two stages. The first ran from the northern side of Harmoni Station to the southern side of Sawah Besar Station over nearly three months, from July to October 2025.
“The next stage saw TBM 2 moved to the northern side of Sawah Besar Station to continue construction towards the southern side of Mangga Besar Station, from February to July 2026,” Weni said in Jakarta on Wednesday.
TBM 2 for CP202 has now broken through the wall at the southern end of the B2 level of Mangga Besar Station.
The completed tunnel will form part of the MRT train route towards Lebak Bulus BSI Station.
Weni said completion of the excavation was also a milestone in the construction of MRT Jakarta Phase 2A, which will connect the Bundaran HI area with Kota Tua.
“The endpoint is also at Mangga Besar Station, but at level B4, around 28 metres below ground,” Weni said.
She said this depth makes the northbound tunnel the deepest railway tunnel in Indonesia.
“We appreciate the hard work of all those who successfully built the two tunnels for the north-south Phase 2A line. We are confident that, in the future, construction of this tunnel will provide valuable knowledge for the development of civil construction in Indonesia,” Weni said.
She added that construction teams used six TBMs to build all the tunnels for the north-south Phase 2A line: two for the stretch from Bundaran HI Bank Jakarta Station to Harmoni Station, two from Harmoni Station to Mangga Besar Station, and two from Mangga Besar Station to Kota Station.
PT MRT Jakarta (Perseroda) is targeting completion and the start of operations on the north-south Phase 2A line’s first segment, from Bundaran HI to Monas, by the end of 2027. The second segment, extending to Kota, is due to be completed by the end of 2029.