MRT Jakarta Completes Indonesia's Deepest Underground Tunnel
PT MRT Jakarta (Perseroda), or MRT Jakarta, has completed construction of the northbound tunnel spanning approximately 5.8 kilometres, connecting Bundaran HI Bank Jakarta Station to Kota Station and linking Phase 1 and Phase 2A of the north-south line.
The completion was marked by a breakthrough moment, when tunnel boring machine 1 successfully reached the end of its excavation and broke through on the southern side of Mangga Besar Station.
“With this achievement, the northbound tunnel of approximately 5.8 kilometres now connects Phase 1 and Phase 2A of the MRT Jakarta north-south line,” said MRT Jakarta Construction Director Weni Maulina in Jakarta on Thursday (9 July).
Weni said the successful completion of the northbound tunnel excavation represents an important milestone in the construction of MRT Jakarta Phase 2A, achieved on target.
Three tunnel boring machines were used by MRT Jakarta and the contractor team to build the northbound tunnel for this Phase 2A section of the north-south line. Each machine worked according to its contract package: CP201 from Bundaran HI Bank Jakarta Station to Harmoni, CP202 from Harmoni to Mangga Besar, and CP203 from Mangga Besar to Kota.
At the breakthrough point on the southern side of Mangga Besar Station, the northbound tunnel lies at a depth of up to 28 metres below ground level.
“This achievement makes it the deepest underground rail tunnel in Indonesia, alongside the tunnel at Sawah Besar Station. A milestone in civil construction in Indonesia,” said Weni.
Tunnel boring machine 1 on package CP202 built the tunnel between Harmoni Station and Sawah Besar Station, approximately 395 metres long, as well as the connecting tunnel between Sawah Besar Station and Mangga Besar Station, which is 800 metres long.
To connect the two stations, tunnel boring machine 1 carried out a crossing beneath the canal located between Jalan Gajah Mada and Jalan Hayam Wuruk.
Weni added that this achievement is the result of thorough planning, good coordination, and the hard work of all parties involved in the construction of MRT Jakarta Phase 2A. Thanks to this synergy, the excavation of the northbound tunnel could be completed according to the established target.
“This success is an important step towards completing the next stages of construction, so that the project can continue to run on schedule,” she said.
The MRT Jakarta construction team and contractors are currently completing the southbound tunnel from Kota to Bundaran HI. All Phase 2A tunnels on the north-south line are targeted for completion in the fourth quarter of 2026, while as of 25 June 2026, construction progress on Phase 2A had reached 61.8 per cent.
PT MRT Jakarta (Perseroda) is targeting completion and operational readiness of Phase 2A of the north-south line by the end of 2027 for the first segment, Bundaran HI to Monas, with the second segment through to Kota due for completion by the end of 2029.