MRT Decision Likely Next Week
The Jakarta Globe By Ronna Nirmala
The Jakarta and national governments are still fighting over who will pay the larger share in the construction of the capital’s Rp 110 trillion ($11.4 billion) railway-based mass rapid transit system.
Jakarta Governor Joko Widodo on Wednesday proposed an investment ratio of 60:40, with the central government taking the larger share, but Finance Minister Agus Martowardojo said that the ratio should be 42:58, with Jakarta pumping more money into the joint financing.
Joko said a decision on the fate of the planned MRT projects could be made as early as next Wednesday. He was speaking after a meeting on investment sharing involving Agus as well as Coordinating Minister for the Economy Hatta Rajasa, State Enterprises Minister Dahlan Iskan and Armida Alisjahbana, the head of the National Development Planning Agency (Bappenas).
“In essence, it is already 90 percent positive [that the project will go forward]. There remains only a decision on the percentage to be borne by Jakarta and by the central government and that will be decided on the 15th [of January],” he said.
Once that decision is reached, the winner of the tender can then be announced, as soon as one day later.
“The tender has already taken place and it is only the coordinating minister’s decision that is still pending. Therefore on the 16th I will decide on the tender, and the MRT can immediately proceed,”
Joko said.
Meanwhile, Agus said after the meeting that it was likely the investment sharing ratio would be kept at the previous arrangement of 42:58, with Jakarta taking the larger share. He said the ratio was agreed on in 2005 between the concerned ministries and the government of Jakarta.
“At that time it was decided that it would proceed with 42 percent in the form of grants from the central government and 58 percent in the form of very long-term soft loans, up to 40 years,” Agus said.
He said a demand to modify the ratio could be discussed but should be based on very detailed computations and estimates.
“It will be the coordinating minister for the economy who will decide whether we can raise our contribution from 42 percent to a higher figure. Any change should take the form of a government decree and there should also be modification of the grant and fund phasing agreements,” Agus said.
The minister said Jakarta should also complete all related studies on the MRT project, especially its feasibility study.
He said that so far a study has been conducted for the segment between Lebak Bulus in South Jakarta and Dukuh Atas in Central Jakarta, but not yet for the second segment that will further extend the line to the railway station in Kota, North Jakarta.
“There needs to be clarity on the project’s coverage and funding because the main key is in the project costs,” Agus said.
Agus said the studies should be carefully conducted, especially regarding costs, so that it does not become too expensive, which would result in the public having to bear the additional costs.
Joko acknowledged that the feasibility studies had not been completed, but said the detailed engineering design for the Dukuh Atas-to-Kampung Bandan segment will be started in March.
He said the feasibility study for the entire line was completed 26 years ago and has repeatedly been updated.
“It has been repeatedly [updated] for 26 years. So, what we need to do now is just do it. At least, we can start from Lebak Bulus to Dukuh Atas first,” the governor said.
Jakarta is set to have 110 kilometers of MRT line, with the first phase of construction to be a mostly underground 14-kilometer line, from Lebak Bulus to the Hotel Indonesia traffic circle in Central Jakarta.
The construction of the Rp 110 trillion MRT project was supposed to start this year, but Joko put it off on concerns about the city’s 58 percent loan from the Japan International Cooperation Agency.
Joko has expressed concerns about its price tag as the MRT will cost Rp 1 trillion per kilometer, and repeatedly expressed his preference for the monorail, which would only require Rp 5.4 trillion, although its network would be less extensive.
But the central government and transportation experts argued that an MRT would be a better solution due to its bigger capacity. The experts have also said the MRT has a clear financial backer, JICA, while the monorail, an elevated system, does not.
“Construction for the MRT in Jakarta must not be postponed. You cannot make more excuses to postpone [the construction] again,” Trisakti University public policy expert Yayat Supriyatna said previously.
Agus Pambagio, a transportation expert from the University of Indonesia, agreed.
“Without the MRT, [Jakarta] will be further behind [other Asian cities]. Indonesia once bid to host the 2002 World Cup but lost because we didn’t have the MRT,” he said.
Source: jawawa.id (https://jawawa.id/newsitem/mrt-decision-likely-next-week-1357750800)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/home/mrt-decision-likely-next-week/565223)