MRT Construction Prompts DKI Jakarta Transport Agency to Implement Traffic Diversions Around Kota Station

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
MRT Construction Prompts DKI Jakarta Transport Agency to Implement Traffic Diversions Around Kota Station
Image: Antara (Indonesian)

The Jakarta Transportation Agency (Dishub DKI) is implementing traffic engineering around Glodok Station and Kota Station in line with the ongoing construction of Mass Rapid Transit (MRT) Phase 2 under contract package CP203.

The works, located on Jalan Pintu Besar Selatan and at the Asemka junction, are being carried out by PT Hutama Karya and will proceed in stages.

Head of Dishub DKI Jakarta Budi Awaluddin said on Wednesday that the traffic engineering is adjusted to the project stages to maintain smooth traffic flow.

“The Kota Station and Asemka junction area will be affected from 10 August 2026 to 15 January 2027,” he said.

On Jalan Pintu Besar Selatan, north-to-south traffic will use the western side up to the Asemka junction. Meanwhile, access on the eastern side will pass through the western area towards Jalan Hayam Wuruk, specifically for Transjakarta buses and building access.

At the Asemka junction, motorists travelling from west to east and vice versa will pass through the northern lane of the tunnel construction area with adjusted road geometry.

Regarding building access, Budi said shophouses and buildings on the western side remain accessible via the existing single lane. If congestion occurs, this section will be opened to general vehicles.

Budi detailed the traffic engineering for the coming period as follows:

Stage 4.1 (10 August – 9 September 2026): Implementation of contra flow on Jalan Hayam Wuruk.

Stage 4.2 (10 September – 9 October 2026): Access to Jalan Kemurnian VI will be closed for construction of the station entrance and diverted through the Hotel Novotel area.

Stage 4.3 (10 October 2026 – 17 May 2027): Access to Jalan Kemurnian VI will be reopened. Conversely, access to Hotel Novotel will be closed. Meanwhile, access to Maxim, Jhony Steak, and JMB Clinic will be diverted through Jalan Kemurnian VI with an open-close system.

Previously, the lifting of Flash Butt Welding equipment on Jalan Pintu Besar Selatan was carried out on 16–22 July 2026 from 11.00 pm to 4.00 am Western Indonesia Time with an open-close system on the Transjakarta lane.

“Dishub DKI urges road users to rely on alternative routes, obey signs and instructions from officers on the ground, and prioritise safety. The project implementer bears full responsibility for the safety of road users during the works,” Budi said.

More from 5 August 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/mrt-construction-prompts-dki-jakarta-transport-agency-to-implement-traffic-diversions-around-kota-station-1785945312)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5681596/pembangunan-mrt-dishub-dki-rekayasa-lalin-di-kawasan-stasiun-kota), translated from Indonesian
Print