Ministry of Transport Accelerates Husein Airport to Serve Jet Flights by 17 August

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
Ministry of Transport Accelerates Husein Airport to Serve Jet Flights by 17 August
Image: Antara (Indonesian)

The Ministry of Transport is preparing Husein Sastranegara Airport in Bandung, West Java, to begin serving jet aircraft on 17 August 2026 through a phased scenario before reaching full operations on 17 September 2026.

Director General of Air Transport at the Ministry of Transport, Lukman F. Laisa, said his office is pushing for the acceleration of operational services based on two reactivation scenarios with different operational targets.

“We have prepared two scenarios. The first scenario targets serving jet aircraft from 17 August 2026, while the second scenario targets reaching full operations on 17 September 2026,” said Lukman in a statement confirmed in Jakarta on Sunday.

Therefore, the Ministry of Transport is encouraging PT Angkasa Pura Indonesia (Persero), also known as InJourney Airports, as the airport operational service provider, to accelerate the fulfilment of all aspects of operational readiness for Husein Sastranegara Airport in Bandung.

“We are urging PT Angkasa Pura Indonesia to promptly follow up on the fulfilment of all aspects of operational readiness,” he said.

He said the Directorate General of Air Transport has completed operational studies and safety assessments as the basis for the airport’s reactivation.

The follow-up on operational readiness is now the responsibility of PT Angkasa Pura Indonesia as the airport operator.

“The entire process must continue to prioritise the principles of safety, security, service and compliance with civil aviation regulations,” Lukman said.

Under the first scenario, Husein Sastranegara Airport is planned to serve flights using jet aircraft with minimal operations, business flights and chartered flights, supported by basic infrastructure readiness.

Meanwhile, under the second scenario, the airport is targeted to serve Boeing 737-800 and Airbus A320 category jet aircraft through the implementation of a slot management system to ensure operational capacity runs safely, orderly and effectively.

To support these targets, PT Angkasa Pura Indonesia is being encouraged to promptly meet various requirements on both the landside and airside.

Work that needs to be accelerated includes the runway and taxiway overlay, rigid apron reconstruction and flexible apron overlay, terminal roof repairs and waterproofing, as well as the improvement of various passenger service facilities.

From an aviation safety perspective, the Directorate General of Air Transport is also urging PT Angkasa Pura Indonesia to promptly meet the Category 7 requirements for Aviation Accident Rescue and Fire Fighting (PKP-PK).

These needs can be met through the mobilisation of Aircraft Rescue and Fire Fighting (ARFF) vehicles from Kertajati Airport after the completion of Hajj pilgrim return operations, accompanied by the strengthening of PKP-PK personnel.

Meanwhile, other supporting equipment needs are expected to be met through the optimisation and mobilisation of existing assets without new procurement, so that the reactivation process can proceed more efficiently.

In its implementation, the Directorate General of Air Transport will continue to coordinate and supervise alongside PT Angkasa Pura Indonesia, the Indonesian Air Force through the Commander of Husein Sastranegara Air Base, and all relevant stakeholders, given that the airport’s operations are conducted on a shared-use basis.

Lukman expressed hope that through intensive coordination and commitment from all parties, PT Angkasa Pura Indonesia can ensure Husein Sastranegara Airport resumes operations according to the targets set under each scenario.

“While continuing to guarantee the aspects of safety, security, service and compliance with civil aviation regulations,” Lukman added.

Husein Sastranegara Airport has special characteristics, with a runway measuring 2,220 by 45 metres, and is an airport used jointly with the Indonesian Air Force.

More from 12 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/ministry-of-transport-accelerates-husein-airport-to-serve-jet-flights-by-17-august-1783860743)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5646371/kemenhub-pacu-bandara-husein-layani-pesawat-jet-perdana-di-17-agustus), translated from Indonesian
Print