Ministry of Public Works Proposes Extension of Transition Period in Four Aceh Regions

| Source: Tempo (Indonesian) Translated from Indonesian | Infrastructure

The Ministry of Public Works’ regional office has proposed an extension of the post-disaster management transition period in four affected regions of Aceh, following an inspection of infrastructure development progress on 2 June 2026. The proposal follows a field visit by the Sumatra Post-Disaster Rehabilitation and Reconstruction Acceleration Task Force (Satgas PRR) alongside BPJN Aceh, BWS Aceh, the BP2JK Lhokseumawe Regional Office, and PT Adhi Karya to the Pidie, Pidie Jaya, Bireuen, and North Aceh regencies between 28 May and 2 June 2026.

Imran, a representative of the National Post-Disaster PRR Task Force, stated that the proposal for the extension was previously discussed during a consolidation meeting on 25 May 2026 in Banda Aceh. He noted that the proposal has been communicated to the Vice Governor of Aceh, the Provincial Secretary, and the Assistant II of the Aceh Provincial Secretariat in a written report addressed to Task Force Head Tito Karnavian on Thursday, 4 June 2026.

According to Imran, the extension is being sought because several strategic infrastructure projects remain in progress, ranging from river embankment management and national road rehabilitation to the construction of permanent bridges in several affected areas. While the emergency response period for disaster management in Aceh is scheduled to end on 23 June 2026, numerous rehabilitation and reconstruction projects are still ongoing and require accelerated completion.

Field conditions support the Ministry’s proposal. During inspections from Pidie to Bireuen, the Task Force and the Ministry of Public Works found ongoing work on boulder installation, river embankment reinforcement, and bridge construction that is still being finalised. In Pidie Regency, the team monitored the installation of 252 metres of boulders at Krueng Baro, Keumala District. In Pidie Jaya, while 375 metres of boulder installation at Krueng Meureudu has been completed, the remaining 625 metres are still in progress. Additionally, embankment repairs near the Meureudu Bridge, spanning 621.2 metres, are currently being handled by BPJN. Work on 425 metres of boulder installation for dam repairs in Pante Lhong, Bireuen Regency, is also ongoing.

Regarding bridge construction, the concreting of support pillars for the Kuta Blang Bridge at Krueng Tingkeum is still underway, with the primary phase targeted for completion by 23 June 2026. Imran added that contracts for bridge construction on national roads will be processed in June, with work commencing in July. The Aceh River Basin Authority (BWS) will accelerate river flow management, while the National Road Implementation Office (BPJN) will expedite national bridge construction. Imran emphasised that the entire series of works is expected to be completed no later than December 2026.

More from 4 June 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/ministry-of-public-works-proposes-extension-of-transition-period-in-four-aceh-regions-1780829142)
Originally published by Tempo (Indonesian) (https://nasional.tempo.co/read/2106834/balai-kementerian-pu-usul-perpanjangan-transisi-di-empat-wilayah-aceh), translated from Indonesian
Print