Ministry of Public Works Completes Lembah Anai Restoration in West Sumatra
Jakarta (ANTARA) — The Ministry of Public Works (PU) has completed post-disaster handling of flash floods and landslides along the Padang Panjang–Sicincin national road section in the Lembah Anai area of West Sumatra.
Public Works Minister Dody Hanggodo said the Lembah Anai section has been functional again since 16 December 2025, and its permanent rehabilitation has now been completed on schedule by July 2026.
“Road and bridge access is the key to logistics movement, emergency services, and community economic recovery. That is why from the start we worked without pause to ensure the region’s isolation could be addressed as quickly as possible. Public safety and smooth mobility are our priorities,” Dody said in Jakarta on Thursday.
The works restored connectivity on the main Padang–Bukittinggi route affected by the hydrometeorological disaster of November 2025.
The works, which began on 28 November 2025, included road body repairs, slope protection, riverbank reinforcement, drainage construction, handling of the Margayasa Bridge, and permanent construction at all affected points, with a contract value of Rp460.11 billion.
“If we repair the road, the embankments must also be treated. Otherwise, the road will not last long. That is why all works in this area are being carried out permanently so they are safer and more sustainable,” Dody said.
According to the West Sumatra National Road Implementation Agency (BPJN), the disaster severed one point of the road body, caused landslides at 19 points, and damaged two bridges along the KM 61+600 to KM 67+400 section.
As the national route linking Padang, Bukittinggi, Riau, and North Sumatra, the closure of this section had forced traffic to be diverted via Sitinjau Lauik.
With the completion of the Lembah Anai works, the Ministry of Public Works continues to strengthen national connectivity through disaster-resilient infrastructure as part of its PU608 commitment to delivering reliable, safe, and beneficial infrastructure for the public.
Source: jawawa.id (https://jawawa.id/newsitem/ministry-of-public-works-completes-lembah-anai-restoration-in-west-sumatra-1785379937)