Ministry of Public Works Accelerates Construction of Kayuagung–Palembang–Betung Toll Road

| Source: Antara (Indonesian) Translated from Indonesian | Infrastructure
Ministry of Public Works Accelerates Construction of Kayuagung–Palembang–Betung Toll Road
Image: Antara (Indonesian)

Jakarta (ANTARA) - The Ministry of Public Works (PU) is accelerating the construction of the Kayuagung–Palembang–Betung Toll Road to strengthen connectivity along the main corridor of the Trans-Sumatra Toll Road.

Public Works Minister Dody Hanggodo emphasised that the toll road’s construction offers significant benefits for public mobility and logistics distribution in Sumatra.

“We continue to support this project’s development to ensure it is completed on time because it provides substantial benefits to the community,” Dody stated in Jakarta on Tuesday.

Two priority sections, namely Section 1 Kramasan–Sungai Rengas and Section 2 Sungai Rengas–Pangkalan Balai, are targeted for completion in the third quarter of 2026.

The Kayuagung–Palembang–Betung Toll Road has a total length of 111.69 km and forms part of the Trans-Sumatra Toll Road network. The Kayuagung–Palembang section, spanning 37.62 km, is already operational, while the extension to Betung, covering 69.19 km, is currently under construction.

According to Dody, the construction of the Palembang–Betung section is divided into three sections: Section 1 Kramasan–Sungai Rengas (21.5 km), Section 2 Sungai Rengas–Pangkalan Balai (33 km), and Section 3 Pangkalan Balai–Betung (14.69 km).

The current acceleration focus is on Sections 1 and 2, as they will enhance connectivity from the Palembang urban area to northern South Sumatra and support smoother inter-provincial logistics flow.

Dody noted that construction progress shows significant achievements. For Section 1, land acquisition has reached 95.43 per cent, with construction progress at 92.07 per cent. For Section 2, land acquisition stands at 95.58 per cent, and construction progress at 89.88 per cent. Both sections are targeted for construction completion in the third quarter of 2026.

Meanwhile, Section 3 Pangkalan Balai–Betung has recorded 86.15 per cent land acquisition progress and 51.82 per cent construction progress, targeted for completion in early 2027.

Dody explained that the toll road’s construction is carried out through a Government Cooperation with Business Entities (KPBU) scheme by the Toll Road Business Entity (BUJT) PT Hutama Karya (Persero). Construction work on Sections 1 and 2 is handled by PT Waskita Karya (Persero) Tbk, while Section 3 is managed by PT Hutama Karya Infrastruktur.

Overall, Dody stated, the Kayuagung–Palembang–Betung Toll Road project has an investment value of approximately Rp14.98 trillion with a 50-year concession period. The toll road’s presence will significantly reduce travel time between Palembang and Betung from around three hours to about one hour.

He added that, besides improving travel efficiency, the toll road is expected to streamline logistics distribution, lower transportation costs, and drive economic growth in the South Sumatra region.

The Kayuagung–Palembang–Betung Toll Road will serve as a crucial component in strengthening the main network of the Trans-Sumatra Toll Road, acting as the backbone for the mobility of people and goods on the island of Sumatra.

More from 5 May 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/ministry-of-public-works-accelerates-construction-of-kayuagung-palembang-betung-toll-road-1777960608)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5554215/kementerian-pu-percepat-pembangunan-tol-kayuagung-palembang-betung), translated from Indonesian
Print