Ministry of Energy: Ungaran Geothermal Development to be Conducted in Stages
With directional drilling technology, drilling can be directed from specific points towards target reservoirs beneath the surface.
Jakarta (ANTARA) - The Ministry of Energy and Mineral Resources (ESDM) has emphasised that the development of the geothermal power plant (PLTP) in the Gunung Ungaran Geothermal Working Area, spanning Semarang and Kendal Regencies in Central Java, will be carried out in stages. This process prioritises technical studies, safety, environmental protection, and the preservation of cultural heritage sites, including the Gedong Songo Temple.
“The project development is currently in the exploration and feasibility study stage. There are still several stages to be completed, and each stage must be based on data, technical studies, environmental aspects, licensing, and social considerations of the community. Exploration is conducted to ensure geothermal potential while assessing the feasibility of its development,” stated Dwi Angge, Spokesperson for the Ministry of Energy and Mineral Resources, in a statement in Jakarta on Wednesday.
Based on the 2025-2034 Electricity Supply Business Plan (RUPTL), the Gunung Ungaran geothermal power plant is planned to have a capacity of approximately 55 MW, with an operational target set for 2031.
To reach the construction stage, developers must first obtain certainty regarding the characteristics and potential of the reservoir through a series of research and exploration activities.
Anggi, as she is commonly known, explained that exploratory drilling is conducted based on geological and geophysical studies to understand subsurface conditions and determine reservoir targets.
Surface drilling locations are not always positioned directly above the geothermal source.
“With directional drilling technology, drilling can be directed from specific points towards target reservoirs beneath the surface. Therefore, the determination of well locations is based on data and technical studies, rather than solely on the surface position of the geothermal source,” she explained.
In its implementation, Anggi continued, the preservation of the Gedong Songo Temple is a crucial consideration.
A social mapping study by Diponegoro University in 2019 identified a zoning system for the area, which includes core, buffer, and development zones.
Geothermal development must adhere to the applicable boundaries and regulations to ensure that the cultural heritage site remains protected.
“The protection of cultural heritage is a component that must be addressed throughout the entire development process. Every planned activity must refer to the applicable zoning regulations and preservation principles,” said Anggi.
In addition to the activity locations, the total area of the working zone must also be understood proportionally.
Of the total 100 per cent of the geothermal working area, the total land used for a 55 MW geothermal power plant is less than 1 per cent.
During the drilling stage, land requirements are also relatively limited and are determined based on technical studies, field conditions, and environmental and spatial planning regulations.
Water and environmental aspects are also part of the studies conducted before moving to the next stage.
The government also ensures that water requirements, potential impacts on the environment and community, and management measures will be assessed during the environmental licensing and permit fulfilment process.
In line with this, according as Anggi, social mapping is conducted to obtain an overview of the conditions of the communities surrounding the activity area, including social aspects, land use, environment, and spatial planning.
This approach is necessary so that development plans can consider the overall conditions of the area and involve the community from the early stages.
“Geothermal development is not just about drilling and power generation. There are community, environmental, spatial, licensing, safety, and cultural preservation aspects that must be considered in an integrated manner,” Anggi emphasised.
The development of the Gunung Ungaran geothermal power plant is a long-term process.
The Ungaran Geothermal Working Area has been established since 2007, and since then, development has been carried out through various stages, ranging from geoscience research and studies, well location determination, preparation and fulfilment of permits, exploratory drilling, feasibility studies, to the decision on construction and operation.
The results of the exploration will serve as a primary basis for determining the feasibility of development.
If the exploration results show reservoir potential that meets technical and economic aspects, and all environmental, safety, and licensing requirements are met, the project may be considered for the next stage of development.
Anggi added that experience in geothermal development in various regions of Indonesia shows that the utilisation of geothermal energy can coexist with other regional functions.
The Dieng experience serves as a relevant lesson for Gunung Ungaran, as geothermal development takes place in an area that possesses geological, biodiversity, cultural, tourism, and agricultural value.
The presence of geothermal facilities in that area can coexist with various community and tourism activities, including cultural activities involving the community and taking place around the geothermal area.
In the context of Gunung Ungaran, Anggi noted, a similar approach can serve as a foundation for building synergy between energy development and the potential for nature and geological tourism, cultural preservation, agriculture, the environment, and community activities around the area.