Ministry of Energy Accelerates Batang Toru Hydroelectric Plant Operations to Anticipate Electricity Crisis

| Source: Antara (Indonesian) Translated from Indonesian | Energy
Ministry of Energy Accelerates Batang Toru Hydroelectric Plant Operations to Anticipate Electricity Crisis
Image: Antara (Indonesian)

The Ministry of Energy and Mineral Resources (ESDM) is accelerating the operations of the Batang Toru hydroelectric power plant (PLTA) in North Sumatra to anticipate an electricity crisis in Sumatra. “This is our acceleration effort for the provision and reliability of energy nationally. Specifically, the energy condition in the Sumatra region is quite critical, so we require anticipation. With the limited availability of other primary energy sources, we have the Batang Toru PLTA which can be integrated into the grid,” stated Deputy Minister of Energy Yuliot in an official statement confirmed in Jakarta on Friday.

Five transmission towers that collapsed due to a hydrological disaster in November 2025 continue to pose challenges to the Sumatran electricity system. The urgency of operating the power plant has increased following the November 2025 disaster, which also damaged supporting infrastructure for the power grid.

“The reconstruction of this transmission line is being carried out in an accelerated manner so that electrical energy from the Batang Toru PLTA can be optimally distributed into the Sumatran transmission network,” said Yuliot.

In addition to transmission constraints, this Rp21.6 trillion project had previously faced delays due to licensing and administrative issues. Certainty regarding its continuation was achieved after the Minister of Environment revoked administrative sanctions through Decree Number 1444 of 2026 on 16 March 2026, followed by approval to proceed with construction.

More from 31 July 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/ministry-of-energy-accelerates-batang-toru-hydroelectric-plant-operations-to-anticipate-electricity-crisis-1785481249)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5673992/esdm-percepat-operasional-plta-batang-toru-antisipasi-krisis-listrik), translated from Indonesian