Minister of Public Works Targets 2 Percent Daily Progress for People's School in West Sumatra
JAKARTA - The Minister of Public Works (PU), Dody Hanggodo, has targeted a minimum daily progress of two percent for the construction of the People’s School (SR) in Dharmasraya Regency, West Sumatra, to ensure the project is completed and ready for use in the new academic year of July 2026.
The target was stated by Dody during his direct inspection of the People’s School construction in Dharmasraya Regency on Wednesday (6/5/2026).
During the visit, he was accompanied by Member of Commission V of the Indonesian House of Representatives Zigo Rolanda, Deputy Governor of West Sumatra Vasko Ruseimy, and Regent of Dharmasraya Annisa Suci Ramadhani.
“As of yesterday afternoon, I coordinated and it’s already around 9 percent. So, hopefully by 20 June it will be finished. There might be some parts that aren’t fully completed, and I’ve already instructed that the grass for the football field be sown soon because it takes quite a long time and can’t be done suddenly. But overall, it’s good,” Dody explained.
According to him, construction acceleration is continuously being carried out to ensure the work is completed on schedule. He even requested that any daily progress delays be caught up the following day.
“So, if today it’s behind by half a percent, then tomorrow it must be 2.5 percent. Because our younger siblings who are currently still at the pioneer People’s School must be able to enter the new school in the new academic year of July 2026,” he added.
Dody also appreciated all parties involved in the People’s School construction, from the Stage 2 People’s School Acceleration Task Force, the Directorate General of Strategic Infrastructure team, to the implementing contractors who continuously monitor daily progress and material readiness on site.
“I saw with my own eyes that the Stage 2 People’s School Acceleration Task Force is working well. The coordination is good. The contractors are also moving quickly. Everyone is working together to ensure daily progress runs smoothly, including material readiness,” he added.
The People’s School is designed as an integrated educational facility from primary school (SD), junior high school (SMP) to senior high school (SMA) levels.
The facilities prepared include dormitories, dining areas, places of worship, sports facilities, a football field, and an athletics track. The government also covers students’ educational needs such as uniforms and books.
The construction of the People’s School is carried out by the Ministry of Public Works as part of efforts to expand access to decent education while supporting the eradication of extreme poverty and improving the quality of human resources.
Meanwhile, West Sumatra’s Deputy Governor Vasko Ruseimy stated that the West Sumatra Provincial Government fully supports the acceleration of People’s School construction as an effort to improve educational access for underprivileged communities.
“The West Sumatra Provincial Government targets the construction of an additional 7 People’s Schools next year with an average area of 8–10 hectares,” Vasko emphasised.