Minister of Public Works says progress on 'people's schools' reaches 78 percent
Jakarta (ANTARA) - The Minister of Public Works (PU), Dody Housand, stated that, on a national average, the progress of ‘People’s School’ (Sekolah Rakyat) construction across various regions of Indonesia has reached 78 per cent.
“We remain optimistic. At a minimum, primary, junior high, and senior high school buildings can be completed first so that students can enter new schools for the new academic year this July. Even if some locations are not yet 100 per cent complete, they must at least be functional,” Dody said in a statement in Jakarta on Monday.
The primary focus of the Ministry of Public Works at present is to ensure that the main buildings—namely primary, junior high, and senior high school levels—are functional and ready for use by mid-July.
Dody highlighted the success of the ‘People’s School 2’ construction project in Sukoharjo Regency, Central Java, which has now entered the “green zone,” meaning it is on track with the planned targets.
This project had previously faced delays due to damage to village roads caused by heavy project vehicles.
“Almost everywhere that utilises public access encounters similar obstacles. Village or regency roads are usually not suitable for heavy machinery. Therefore, service providers (contractors) must put in extra effort, such as through CSR, to prepare or repair the access roads beforehand,” he said.
Dody cited a similar challenge in Brebes, where the implementers had to construct a temporary Bailey bridge.
“This was done so that the distribution of logistics would not disrupt the activities of local residents,” he added.
Specifically for the work in Sukoharju, Dody targets physical readiness to reach over 90 per cent by the deadline.
Dody also mapped out the differing construction challenges between Java and regions outside Java. In Sukoharjo and other parts of Java, the greatest challenge currently lies in the architectural and finishing phases.
“This phase requires the most time because it is highly dependent on detail and the availability of skilled labour,” he said.
Meanwhile, for ‘People’s School’ projects outside Java, such as in Sumatra, Maluku, and Sulawesi, the main obstacle is logistical infrastructure.
“The problem lies in the logistical road access from the nearest port or airport to the specific location of the school. Every location has its own unique issues, and we are finding solutions one by one to ensure completion by the end of June,” Dody said.
The massive construction of these ‘People’s Schools’ is more than just a standard infrastructure project. He emphasised that this is a direct mandate from President Prabowo Subianto to break the cycle of extreme poverty in Indonesia through education.
Source: jawawa.id (https://jawawa.id/newsitem/minister-of-public-works-says-progress-on-peoples-schools-reaches-78-percent-1781506407)