Minister Dody Says Semarang Sewer Main Project Is Ahead of Target, but Faces This Obstacle

| Source: VIVA.co.id Translated from Indonesian | Infrastructure
Minister Dody Says Semarang Sewer Main Project Is Ahead of Target, but Faces This Obstacle
Image: VIVA.co.id

Construction of the domestic wastewater main network in Semarang, Central Java, has recorded physical progress of more than 20 per cent.

The achievement is ahead of the original plan, which put progress at 10 per cent, although the project has encountered difficulties because of narrow road access.

Public Works Minister Dody Hanggodo said limited road width was the main challenge in carrying out the project. This meant the work could not be undertaken simultaneously on a large scale.

“I just wanted to see the progress on site and how quickly it is advancing. Given the fairly narrow road access, this is indeed a significant obstacle for the contractor in working at full speed,” Minister Dody said on Monday (23 November 2026).

Dody explained that work on a road section of around 1.4 kilometres had to be carried out in stages. Once one section is completed, the area will be closed off and work will move to the next section, allowing nearby residents to continue their activities.

Despite these difficulties, Dody praised the project for exceeding its target. He said the progress target for this year had previously been set at around 13 per cent, while work on the ground had already surpassed 20 per cent.

He said coordination and traffic management during construction had gone well. He hoped the road section currently under construction could be completed by the end of 2026.

“The only obstacle is the narrow road access; there is nothing else. This narrow-road section can be completed by the end of this year. However, the overall project will take longer, until around 2028,” he said.

The Main Trunk Sewer Installation CWIS-02 project, being carried out by the Directorate General of Human Settlements, involves building a main network to channel domestic wastewater to a wastewater treatment plant (WWTP).

The main network is designed to be 10,658 metres long and includes 37 manholes. The system is also supported by two groups of pumping stations, with maximum flow capacities of 280 litres per second and 398 litres per second respectively. The two pumping stations have head capacities of 35 metres and 21 metres respectively.

Tags: berita

More from 23 November 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/minister-dody-says-semarang-sewer-main-project-is-ahead-of-target-but-faces-this-obstacle-1795449098)
Originally published by VIVA.co.id (https://www.viva.co.id/berita/nasional/1945855-menteri-dody-sebut-proyek-jaringan-utama-air-limbah-semarang-lampaui-target-tapi-ada-kendala-ini), translated from Indonesian
Print