Mining Giants Sign Processing Agreements
The Jakarta Globe By Tito Summa Siahaan
With the 2014 ban on mineral exports looming, two mining giants announced on Tuesday that they signed landmark agreements to supply their concentrates to local processing firms that plan to build smelters.
Rozik B. Soetjipto, president director of Freeport Indonesia, on Tuesday signed a memorandum of understanding with Indovasi Mineral and Indosmelt to supply them with concentrates should the companies’ plans to build processing facilities be successful.
Martiono Hadianto, the president director of Newmont Nusa Tenggara, disclosed that his company had also signed a similar agreement with the two firms.
Under the plan, Indovasi will build a processing facility with a production capacity of 200,000 tons of copper cathode, while Indosmelt’s facility will have output of around 120,000 tons of copper cathode and up to 30 tons of gold a year. The projects will cost around $1.5 billion each.
However, the facilities are still on the drawing board and will likely be completed in 2017, meaning that the MoU signed by both Freeport and Newmont will still miss the 2014 deadline set by the government that will ban the exporting of raw minerals for processing.
For that reason, both Rozik and Martiono requested a deadline extension from the government to allow for time to build the facilities so minerals can be processed domestically.
Currently, 30 percent to 40 percent of output from Freeport’s and Newmont’s mining sites is processed in a smelting facility in Gresik, East Java.
“Our commitment [to support the government’s program] is clear, but it must be done in phases and realistically. We plead for the government to understand the circumstances and be more flexible,” Rozik told a news conference on Tuesday.
Martiono echoed Rozik’s opinion, requesting the government be “considerate” in implementing its program.
“They must have known that it [the deadline] is impossible [to meet]. I heard that the government is in talks to seek the best solutions possible,” he added.
But the government appears to have little flexibility on the matter, as the 2009 Mining Law states that the raw mineral export ban will be imposed next year.
Thamrin Sihite, the director general of coal and mineral resources at the Energy and Mineral Resources Ministry, said the agreements signed by Freeport and Newmont will have little impact on the circumstances of the law.
“We are always consistent with the law. The only way to alter it is either by revising the law, which is difficult, or issuing a government regulation in lieu of law [Perpu],” he said.
Thamrin pointed out that postponing the export deadline would be unfair to companies that have already invested heavily in smelting facilities to comply with the government’s program.
Dede Indra Suhendra, the ministry’s director of minerals, said that miners like Freeport and Newmont will have had at least five years to meet the deadline, which was finalized in 2009.
Furthermore, during the drafting of the law, the government was informed by miners that building a smelter would only take three years, Dede said.
Thamrin and Dede claimed the government had nothing to lose if the export ban is imposed as scheduled.
“There will be no revenue loss should Freeport and Newmont stop shipping their concentrates abroad, because the resources will still be there, contained within the soil,” Thamrin said.
Freeport has operations in Papua while Newmont operates the Batu Hijau mine on Sumbawa island in West Nusa Tenggara.
Miners have long warned that the time frame for the export ban is unrealistic.
Source: jawawa.id (https://jawawa.id/newsitem/mining-giants-sign-processing-agreements-1376413200)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/business/mining-giants-sign-processing-agreements/)