Level Crossing in Pasar Minggu to be Closed Once Parallel Rail Road is Completed
Jakarta Governor Pramono Anung has inspected the construction of the access road parallel to the railway tracks in Pasar Minggu, South Jakarta, which is targeted for completion in 2027. The level crossing at Jalan Purbaya, or Simpang Volvo, in Pasar Minggu, will be closed as a result of this project.
“The Volvo crossing will be closed, Sir, later on. Once this road is completed, the Volvo intersection will be closed. This way, there will no longer be a level crossing between the road and the railway, which will certainly help avoid accidents,” said the Head of the Jakarta Provincial Public Works Agency, Heru Suwondo, in Pasar Minggu, South Jakarta, on Monday (14/9/2026).
He noted that there are many level crossings throughout Jakarta. According to him, most of these crossings are small in size, making it difficult to transform them into grade-separated crossings.
“If the crossings are quite small, it is certainly difficult for us to implement grade-separated intersections. What we are building is a replacement for the level crossing between the road and the railway tracks where the road serves as a major route,” he added.
Previously, Pramono set a target for the parallel rail road project in Pasar Minggu to be finished by 2027. He mentioned that the project has been ongoing for a long time but has yet to be completed.
“This morning, the Jakarta Provincial Government, through the Public Works Agency and myself, conducted a re-inspection of the road that was actually planned since the era of Bang Foke in 2013, but remains unfinished to this day,” Pramono told journalists in Pasar Minggu, South Jakarta, on Monday (14/9).
Pramono stated that land acquisition around the road construction is already 70% complete. He expressed hope that the land acquisition process would proceed smoothly so that the project could be completed according to the target.
Pramono noted that the 1.7-kilometre-long road will have a width of 18 to 23 metres. He believes that the new road will significantly ease access for residents.
Source: jawawa.id (https://jawawa.id/newsitem/level-crossing-in-pasar-minggu-to-be-closed-once-parallel-rail-road-is-completed-1789365542)
Originally published by detikcom (https://news.detik.com/berita/d-8661842/perlintasan-sebidang-di-pasar-minggu-akan-ditutup-usai-jalan-sejajar-rel-tuntas), translated from Indonesian