Led by Purbaya, These Are the Results of the Hearing on Resolving Business Obstacles for the Saguling Floating Solar Power Plant
Finance Minister Purbaya Yudhi Sadewa emphasised that the expansion of the Satgas Debottlenecking’s authority represents a tangible demonstration of the state’s seriousness in improving the investment climate.
“This shows the government is serious; we’re not playing around. This step is fully supported by the President and all ministries. So I’m confident that one year from now, by the end of the year, the investment climate here will have changed dramatically compared to last year,” Purbaya stated firmly at the Ministry of Finance headquarters in Jakarta on Thursday, 7 May 2026.
This aligns with Purbaya’s remarks following his leadership of the ninth open session on resolving business obstacles or debottlenecking, facilitated by the Satgas P3M-PPE. This first complaint session focused on clearing permitting hurdles for the Floating Solar Power Plant (PLTS) Saguling project, undertaken by PT Indo ACWA Tenaga Saguling. PT IATS is a joint venture between PT PLN Indonesia Power Renewables (IPRen) and the multinational energy company ACWA.
The Floating PLTS project is designed to utilise part of the Saguling Reservoir area in West Java, with a projected total capacity of 60 Megawatt alternating current (MWac). PT Indo ACWA Tenaga Saguling has signed a Power Purchase Agreement with PT PLN (Persero) on 13 August 2024.
ACWA Power Indonesia’s CEO, Tim Anderson, explained that his company has allocated USD 10 billion for the first phase of investments in Indonesia. These fresh funds are focused on new renewable energy (EBT) projects, gas turbines, desalination, and green hydrogen development.
Specifically for the Saguling Floating PLTS, the investment amounts to USD 80 million. The construction concept includes 11 floating solar PV islands that will float on the Saguling Reservoir, adjacent to the existing 700-megawatt Hydroelectric Power Plant (PLTA).
Anderson explained that the project has already obtained environmental analysis documents in 2025. These include the Environmental Impact Analysis (Amdal) for the power plant area, Amdal for special facilities, and the Environmental and Social Impact Assessment (ESIA) to meet foreign funding requirements.
However, he said the current critical path development phase is hindered by permits for special facilities. The project requires building a transmission network and substation that must cross 4.4 kilometres of land owned by the Ministry of Forestry. To utilise it, the company must obtain Forest Area Utilisation Approval (PPKH).
Representatives from the Ministry of Forestry, present at the session, stated that the PPKH cannot yet be issued due to one administrative requirement: the absence of a recommendation letter from the West Java Governor.
Addressing this impasse, West Java Provincial Secretary Herman Suryatman, representing the regional government, expressed readiness to issue the recommendation letter with several preconditions.
First, the West Java Provincial Government (Pemprov Jabar) is demanding that PT PLN Indonesia Power fulfil its obligation to provide 1,081 hectares of replacement land in West Java. Currently, this obligation has only been met by 14.7 percent, or about 159 hectares. Second, Pemprov Jabar is requesting that PT ACWA Power Indonesia commit to not felling trees during the electrical installation construction process.
“The recommendation letter from the Governor will be issued by us soon, but PLN must also commit to fulfilling the remaining replacement land in a not too long timeframe. For ACWA, this no-tree-felling commitment must be formalised through an integrity pact,” said the West Java Provincial Secretary.
In response to these conditions, PT PLN Indonesia Power Director Bernadus Sudarmanta expressed his readiness. In line with Finance Minister Purbaya’s directives, PLN Indonesia Power commits to completing the fulfilment of the remaining replacement land no later than 2027.
In agreement with PLN Indonesia Power, Tim Anderson also assured that ACWA Power Indonesia will meet the demands of Pemprov Jabar. His side will prepare a draft Memorandum of Understanding to accommodate all environmental requirements proposed by the West Java Provincial Government.
With the agreement reached in the debottlenecking session, Pemprov Jabar targets to officially submit the Governor’s recommendation letter next Monday, alongside the signing of commitment pacts from PLN Indonesia Power and ACWA Power Indonesia.