Latest Update on Puncak Toll Road Project from Minister of Public Works
The Puncak Toll Road project, which connects Caringin-Puncak-Cianjur, has not yet entered the construction phase. The government is still awaiting the completion of the feasibility study (FS) before the project can proceed to the next stage.
Minister of Public Works Dody Hanggodo revealed that the feasibility study for the project is not yet finished. This means that the physical construction of the Puncak Toll Road cannot begin in the near future.
“It seems the FS is not yet complete. As far as I know, the FS appears to be unfinished,” Dody told reporters on Wednesday (2/9/2026).
The Puncak Toll Road is planned to span approximately 52 kilometres and is divided into five sections. This toll road will eventually connect with the Bogor-Ciawi-Sukabumi (Bocimi) Toll Road and continue through to Cianjur.
Regarding the project stages, the completion of the FS is the prerequisite before technical work and the procurement of business entities can be conducted. The government is currently pushing for the study process to be finalised within this year.
“If possible, I would request that it be completed as quickly as possible this year,” said Doody.
Once the FS is complete, the project will not immediately enter the construction phase. The government must still prepare the Detailed Engineering Design (DED) and complete the tendering process before physical work can commence.
“So, it can then proceed with the DED and so on, so that physical work can begin next year,” said Dody.
Given these stages, the construction target for the Puncak Toll Road is set for 2027. However, this target depends on the smooth completion of the FS, DED, and the tendering process, which are prerequisites for physical development.
The plan for the Caringin-Puncak-Cianjur Toll Road was previously presented by the Toll Road Regulatory Agency (BPJT). The project is estimated to require an investment of approximately Rp24.37 trillion and is expected to serve as an alternative access route to the Puncak area, which has long faced traffic congestion issues.
Although the physical target is aimed for next year, Dody emphasised that the project must still undergo the procurement process first. Consequently, the project’s current status remains in the preparation stage, rather than construction.
“(After that) then it goes to the tender, into the tender stage,” said Dody.