Land Ready: Aceh Tamiang and Bener Meriah to Receive Additional Permanent Housing Allocations

| Source: detikcom Translated from Indonesian | Infrastructure
Land Ready: Aceh Tamiang and Bener Meriah to Receive Additional Permanent Housing Allocations
Image: detikcom

The Ministry of Housing and Residential Areas (PKperumahan dan Kawasan Permukiman - PKP) is adjusting the allocation for the construction of communal permanent housing (huntap) in Aceh, North Sumatra, and West Sumatra based on land readiness. Allocations from regions where land is not yet available are being redirected to areas ready for construction to ensure the target of 7,952 units by 2026 is achieved.

This adjustment is being implemented without reducing the total number of planned permanent housing units. Following the 2026 construction phase, the Ministry of PKP will continue the development of 17,654 permanent housing units in 2027 for communities affected by disasters across the three provinces.

Teddy Paul H. Siagian, Expert Staff for Land, Integrated Development, and Spatial Planning at the Ministry of PKP, stated that land readiness is a critical factor in ensuring construction can proceed immediately. “This is our action plan: 7,952 units must be completed this year, and 17,654 units for next year,” Teddy said in a statement on Thursday (3/9/2026).

He shared this during the Progress Meeting for Post-Disaster Rehabilitation and Reconstruction in Sumatra, held at the PRR Task Force Post, Ministry of Home Affairs, Jakarta, on Wednesday (2/9).

In Aceh, adjustments were made because some permanent housing needs in North Aceh Regency were not supported by available land. This situation necessitated the transfer of some allocations to prevent construction delays.

Specifically, 64 units have been redirected to Bener Meriah Regency, which has prepared the necessary land. With this adjustment, construction originally planned for 2027 can be brought forward to 2026.

Aceh Tamiang Regency has also received an additional 187 units. The permanent housing allocation for the area has increased from the initial 2,212 units to 2,399 units for construction in 2026.

Similar adjustments have been made in West Sumatra. An allocation of 120 units for Tanah Datar Regency has been removed from the Ministry of PKP programme as those units have already been constructed by Danantara. Meanwhile, the allocation from Padang Panjang City has been redirected so that Lima Puluh Kota Regency can construct 204 permanent housing units in 2026.

Regarding procurement, the construction of permanent housing is being prepared through 50 work packages. So far, 15 construction packages have reached the winner announcement stage, while five supervision packages have also identified winners.

The Ministry of PKP is also simplifying the packaging process by merging construction projects in neighbouring villages. This strategy is being applied to reduce the number of excessively small packages and to accelerate the execution of work on the ground.

“Therefore, the target of 7,952 units for this year can still be achieved. No construction targets will be left behind,” said Teddy.

The reallocation and simplification of work packages are part of an effort to ensure that budgets and construction capacity are directed towards locations that are ready for development.

More from 3 September 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/land-ready-aceh-tamiang-and-bener-meriah-to-receive-additional-permanent-housing-allocations-1788418894)
Originally published by detikcom (https://news.detik.com/berita/d-8646481/lahan-siap-aceh-tamiang-dan-bener-meriah-dapat-tambahan-alokasi-huntap), translated from Indonesian