Land Clearing a Major Block in Toll Road Development

| Source: The Jakarta Globe

The Jakarta Globe By Eko Adityo Nugroho

A land clearance backlog has hindered the country’s target to complete 1,045 kilometers of toll roads by this year, a target set in The National Medium-Term Development Plan 2014.

Governments and toll road companies are likely to complete 373.4 km by the end of this year, or less than a third of original target, according to data from the Ministry of Public Works.

Fachtur Rochman, chairman of Indonesian Highway Association (ATI), said the government must support toll road operators in land procurement, which has been an obstacle so far in development of the much-needed roads.

“More often than not toll road developments miss their projected target dates,” Fachtur said.

The government passed a land acquisition law in 2012, which stated that landowners must sell if the land has been designated for a public project, such as dams, transport facilities including roads and railways, drainage systems or “other projects” considered by the president as serving the public interest.

In practice, the implementation was still lagging. Fachtur noted that any ongoing land procurement process before the 2012 law comes into effect would proceed under the previous law.

The government has set the deadline for Dec. 31, 2014 for the 2012 law to go into full effect.

“Since it’s still the beginning of the year, it is difficult to decide which toll roads will use the new regulation. In the middle of 2014 we should be able to decide which toll roads will use the new regulations,” Fachtur said.

Public Works Minister Djoko Kirmanto said last week that the target on toll road development was unlikely to be completed because of the problem with land procurements.

He said this year the government was likely to only finish an additional 13 km of toll road.

That includes several lines: The Cileunyi-Sumedang-Dawuan (3 km); Medan-Kualanamu-Tebing Tinggi segmented Medan-Lubuk Pakam (5 km); access to Tanjung Priok highway (2 km); Solo-Ngawi segmented Solo-Karanganyar (5.6 km); and the Ngawi-Kertosono segmented Saradan-Kertosono (1.6 km).

Despite missing the target in toll road development, Djoko said the ministry has built 2,968 km of regular roads, more than double of its target.

In the Global Competitiveness Index 2013-2014 report published by the World Economic Forum, Indonesia rose to number 38 from number 50 out of 148 countries, thanks to infrastructure improvements.

More from 7 January 2014 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/land-clearing-a-major-block-in-toll-road-development-1389027600)
Originally published by The Jakarta Globe (http://www.thejakartaglobe.com/business/land-clearing-a-major-block-in-toll-road-development/)
Print