Lack of EIA and Building Permits Leads KDM to Halt AI Data Centre Project in Jatiluhur

| Source: CNN Indonesia Translated from Indonesian | Infrastructure
Lack of EIA and Building Permits Leads KDM to Halt AI Data Centre Project in Jatiluhur
Image: CNN Indonesia

The Governor of West Java, Dedi Mulyadi (KDM), has emphasised that the temporary suspension of the artificial intelligence (AI) based data centre construction in the Jatiluhur area, Purwakarta, is a measure to enforce regulations and protect public interests.

The large-scale AI facility project, valued at Rp3.5 trillion, is being undertaken by the data centre developer Big Data Exchange (BDx) Indonesia.

“When I asked yesterday, the Building Permit (IMB) had not been issued. Has the Environmental Impact Assessment (Amdal) been released? Not yet. So, I said do not proceed with the construction yet. Since the permits have not been issued. Where is the error? With the Purwakara Local Government? No. The error lies with the consultants, who had not even submitted the data by the time I arrived,” KDM stated in Bandung on Friday (2/10).

He emphasised that the West Java Provincial Government remains objective. Input from academics at the University of Indonesia (UI) is also being utilised to test the project’s feasibility.

“Personally, if objectively the EIA passes, then there is no problem with proceeding. If the EIA says it is not permitted, then it must be stopped. However, one note: the residents of Purwakarta, who sacrifice for the interests of the Jatiluhur Reservoir, must have access to water. It must not be disrupted,” KDM said.

Regarding the water supply, which is a vital requirement for the cooling system of BDx Indonesia’s AI servers, KDM ensured that the capacity of the Jatiluhur Reservoir is more than sufficient without affecting the residents’ allocation. The cooling system for the BDx data centre facility is planned to utilise the water allocation from the Purwakarta Regency Water Utility Company (PDAM), which has not been optimally utilised to date.

“PDAM is allocated 3,000 litres per second. For decades, only 380 litres per second, or just 11%, has been used. This means 89% of the water remains unutilised. Now, an additional 14% will be used by the company (BDx). Is there still a shortage or a surplus? There is still a surplus. It is simple,” he said.

Previously, KDM personally inspected the site of the BDx AI data centre in Jatiluhur on Tuesday (28/7) to ensure the investment is situated on land safe from the threats of floods, earthquakes, or volcanic activity, and to check the readiness of the water and electricity supply for operations.

More from 2 October 2026 →

Cite this article
Source: jawawa.id (https://jawawa.id/newsitem/lack-of-eia-and-building-permits-leads-kdm-to-halt-ai-data-centre-project-in-jatiluhur-1790945735)
Originally published by CNN Indonesia (https://www.cnnindonesia.com/nasional/20261002182253-25-1411064/belum-ada-amdal-dan-imb-kdm-stop-proyek-data-center-ai-di-jatiluhur), translated from Indonesian
Print