KSP Supports Completion of Harbour Road II Toll Road to Streamline Logistics
The Presidential Staff Office (KSP) supports the completion of the Harbour Road II (HBR II) Toll Road, specifically the Ancol Timur–Pluit section, in order to maintain smooth transportation and the movement of national logistics through Tanjung Priok.
Acting Deputy IV of the Presidential Chief of Staff Fadjar Dwi Wishnuwardhani, during an inspection in North Jakarta on Thursday, said the elevated toll road being constructed by PT Citra Marga Nusaphala Persada Tbk. (CMNP) is being pushed to be completed as soon as possible to ease congestion in the area and safeguard national logistics access at Tanjung Priok Port.
“We are also moving together to assist whenever there are matters that need to be addressed jointly to carry out debottlenecking should there be problems on the ground. Once again, this is not about who is implementing it, not CMNP, not WIKA, but this is a national strategic project that we must ensure runs smoothly,” said Fadjar.
As of July 2026, total construction progress for HBR II has reached 44.12 percent. Land acquisition has reached 253,291 square metres, or 64.57 percent of the total land target, while land ready for construction stands at 319,895 square metres, or 81.55 percent of the target.
Regarding the latest progress, Fadjar said the achievement has actually exceeded the schedule set through July 2026, with the overall construction completion target being the first quarter of 2028.
“This means if the question is how to accelerate it, this is already faster than the target, with the new target, but the hope remains that it can be completed as soon as possible. Why? Because in our view, once again, this toll road and several other toll roads are national strategic programmes and are highly strategic in nature to help the economy as well as transportation and logistics in Indonesia,” he said.
On the same occasion, Director General of Highways at the Ministry of Public Works Roy Rizali Anwar expressed appreciation that the toll road is being built entirely by domestic human resources and without using the state budget (APBN).
“Because indeed the President’s instruction is that we push as much as possible for projects without using the APBN,” said Roy.
He assured that the government will continue to support and evaluate the toll road construction and expects the completion target of the first quarter of 2028 to be achieved.