KRL Green Line Headway to be Reduced to 4-5 Minutes
The President Director of PT KAI, Bobby Rasyundin, has announced plans to reduce the headway for the Rangkas Bitung KRL route. He stated that the current arrival intervals of 10-15 minutes will be shortened to 4-5 minutes.
Bobby shared this information during a Hearing (RDP) with Commission VI of the House of Representatives (DPR) on Wednesday (23/09/2026). He initially presented plans to improve facilities and infrastructure in response to the 1.1 million daily passengers using the Jabodetabek KRL network.
“For the route towards Rangkas, we will also increase and improve the signalling system, so that the current 10-15 minute headway will be shortened to 4 or 5 minutes, transitioning from the previous SF12 configuration,” Bobby said during the meeting.
Regarding the Rangkas Bitung Green Line, he noted that the company has begun installing five traction substations. KAI aims that by 2027, the entire Rangkas Bitung line will be serviced by 12-car train sets.
“The ‘quick win’ infrastructure plan for 2026 involves the Rangkas Bitung Green Line; we are starting the installation of five traction substations this year and upgrading nine other substations. Consequently, by the first semester of 2027, the Green Line will be able to accommodate SF12 sets entirely,” he explained.
KAI also plans to extend the Bekasi Line route to Cikampek in 2027. For the southern route, which currently only reaches Bogor, the service will be extended to Cigombong.
“Similarly, there will be engineering adjustments on the Bogor line, where the Nambo Line will terminate via Citayam, which will add 22 slots towards Bogor. This will increase the capacity of the Bogor Line by more than 30 per cent compared to current levels,” said Bobby.
“Furthermore, we are extending the Overhead Catenary System (LAA) electrification. Currently, the Bekasi Line only reaches Cikarang, but we will extend it towards Cikampek in 2027. Likewise, the southern route, which currently only reaches Bogor, will be extended to Cigombong,” he added.
Source: jawawa.id (https://jawawa.id/newsitem/krl-green-line-headway-to-be-reduced-to-4-5-minutes-1790229747)
Originally published by detikcom (https://news.detik.com/berita/d-8676984/headway-krl-green-line-bakal-dipangkas-jadi-4-5-menit), translated from Indonesian