KPPU Hears Alleged Bid-Rigging Case over Rp70.4 Billion Gresik Sehati Hospital Project
Jakarta (ANTARA) – The Business Competition Supervisory Commission (KPPU) has begun hearing a case concerning alleged collusion in the 2023 tender for the construction of Gresik Sehati Hospital in Gresik Regency, East Java. Case No. 21/KPPU-L/2026 concerns alleged violations of Article 22 of Law No. 5/1999 on the Prohibition of Monopolistic Practices and Unfair Business Competition. The first hearing was held on Tuesday, 24 November 2026, at the KPPU headquarters in Jakarta. Its agenda included the investigator’s presentation of the Alleged Violation Report (LDP) and an examination of the completeness and relevance of documentary evidence and supporting documents. The hearing was chaired by KPPU commissioner Mohammad Reza, alongside KPPU Deputy Chair Hilman Pujana and commissioner Eugenia Mardanugraha, who served as members of the Commission Panel.
The case involves three respondents: PT Pandawa Land Nusantara (formerly PT Permata Lansekap Nusantara), as Respondent I; PT Jaya Semanggi Enjiniring, as Respondent II; and the Selection Working Group for Procurement Package 30, Gresik Sehati Hospital, FY2023, as Respondent III. When the tender took place between April and June 2023, Respondent I was still operating under the name PT Permata Lansekap Nusantara. Respondent I did not attend the first hearing, Respondent II joined remotely, and Respondent III attended in person at the KPPU hearing room.
The hospital construction tender had a budget ceiling of Rp76.264 billion, sourced from the 2023 regional budget (APBD), and an Owner’s Estimate (HPS) of Rp70.479 billion. The construction work was to be carried out in Kedamean District, Gresik Regency. The tender used a one-file post-qualification method, with the lowest-price evaluation system and a pass/fail method, under a unit-price contract. Of 124 prospective bidders who registered, 18 submitted bids by 8 May 2023. Four of these were subsequently evaluated further.
In the LDP, investigators said Respondent II submitted the lowest bid, at Rp55.95 billion, or 79.38 per cent of the HPS. As its bid was below 80 per cent of the HPS, Respondent II was asked, in a letter dated 9 May 2023, to clarify the reasonableness of its price by 12 May 2023. It did not respond and was therefore disqualified. Respondent I, whose bid was Rp59.20 billion, or 84 per cent of the HPS, was then named the tender winner on 17 May 2023. The contract was signed on 13 June 2023, with a 202-calendar-day completion period. The difference between Respondents I and II’s bids was about Rp3.255 billion, equivalent to 4.62 per cent of the HPS.
During the examination, investigators also identified several alleged links between the respondents that they said may be connected to the suspected tender arrangement. First, the two bidding companies used the same subcontractor: PT Lansekap Karya Abadi.
Second, investigators found links in company ownership and management. Their findings included individuals appearing in the management histories of both Respondent I and Respondent II, and the companies’ directors having held management positions in each other’s firms at different times. Some managers from both companies were also listed as officers of PT Lansekap Karya Abadi. Documents and witness testimony further indicated family relationships and links within the same business group.
Third, investigators cited inconsistencies in subcontracting support documents. In its technical bid, Respondent I listed PT Gentayu Cakra Wibowo as a specialist supplier for medical gas work. However, during an examination on 26 June 2025, a witness from that company said it had neither provided a letter of support nor carried out work for Respondent I in the tender concerned.
On the basis of these facts, investigators suspect horizontal collusion between Respondents I and II that created the appearance of competition in the tender. They also suspect vertical collusion involving Respondent III, alleging that it approved and/or facilitated the arrangement, including through an evaluation process that was not sufficiently thorough.
Investigators concluded that the elements of an alleged violation of Article 22 of Law No. 5/1999 had been met. Their conclusion was based on witness testimony, evidence from procurement and legal experts, letters and/or documents, indications, and statements from the respondents. However, all the allegations and conclusions remain the investigators’ claims and will be tested during the proceedings. The Commission Panel has sole authority to assess the case and reach a final conclusion.
The next hearing is scheduled for Tuesday, 8 December 2026, when the respondents are due to present their responses to the Alleged Violation Report.
Source: jawawa.id (https://jawawa.id/newsitem/kppu-hears-alleged-bid-rigging-case-over-rp70-4-billion-gresik-sehati-hospital-project-1795582410)
Originally published by Antara (Indonesian) (https://www.antaranews.com/berita/5876647/kppu-sidang-dugaan-persekongkolan-tender-pembangunan-rs-gresik-sehati-senilai-rp704-miliar), translated from Indonesian