KPK Identifies 8 Corruption Hotspots within Ministry of ATR/BPN Following Summarecon Sting Operation
The Corruption Eradancy Commission (KPK) has disclosed eight corruption hotspots within the Ministry of Agrarian Affairs and Spatial Planning/National Land Agency (ATR/BPN). These vulnerabilities had previously been reported to the Ministry for follow-up, prior to the sting operation (OTT) involving bribery in the management of Summarecon’s Building Use Rights (HGB).
KPK Spokesperson Budi Prasetyo revealed that investigators identified these eight high-risk points through a study conducted by the KPK’s Directorate of Prevention and Monitoring. All identified points fall into two main vulnerable areas: the issuance of certificates and the governance of Cultivation Rights (HGU) issuance.
The eight hotspots include low access to services, delays in service completion, additional land service fees, and the failure to hand over completed files. Furthermore, the findings highlighted issues regarding the supervision of certificate issuance, deviations from Standard Operating Procedures (SOP) for HGU issuance, a lack of HGU certificate mapping, and insufficient oversight of HGU issuance.
“The results of the study show that the average failure to meet Service Level Agreements (SLA), measured by the timeliness of service completion, remains very high,” Budi stated in Jakarta on Saturday (19/09/2026).
Budi detailed that the average SLA failure rate for land services in the Jabodetabek area stands at 73.49 per cent. Three ATR/BPN offices in the Jabodetabek region recorded the highest rates of service delays: the Depok City Land Office (91.14 per cent), Bekasi Regency (87.5 per cent), and Bogor Regency (86.9 per cent).
“The largest SLA failures occurred in three types of services: transfer of rights through sale and purchase (90.3 per cent), changes to land rights (73.4 per cent), and the discharge of mortgages (73.3 per cent),” Budi said. Additionally, the KPK identified issues regarding costs.
According to Budi, 63.83 per cent of service users reported paying additional fees beyond the official rates. Of that number, 53 per cent of respondents stated that these additional costs reached more than 200 per cent of the official fee.
“The KPK has identified deviations in the SOP for HGU issuance within the land sector. Based on HGU service data (granting, extension, and renewal), there are deviations regarding timing and other additional costs,” Budi added.
Furthermore, he continued, HGU services exceeding the SLA in 2021 reached 61 per cent. According to information from the Indonesian Palm Oil Association (Gapki), the average delay in HGU issuance beyond the SLA ranges from four months to as much as 6–12 months. In 2021, the Kutai Timur Land Office held the highest number of HGU files exceeding the SLA, accounting for approximately 24 per cent of national files.
“The percentage of SLA failures in the three Land Offices with the highest volume of HGU services were Kutai Kartanegara (100 per cent), Sumbawa Regency (80 per cent), and Kutai Timur (71 per cent),” Budi explained.
He further explained that the KPK study also uncovered the existence of unofficial additional fees. Based on in-depth interviews with Land Deed Officials (PPAT), unofficial additional costs for HGU issuance are estimated to be 250 per cent of the Non-Tax State Revenue (PNBP).
Based on these findings, the KPK has recommended several remedial measures for the Ministry of ATR/BPN. However, according to Budi, it appears the Ministry of ATR/BPN treated these field facts as inconsequential, leading to the recent sting operation.