Kemang Pratama Bridge in Bekasi Expected to be Reopened by August 2026
The Ministry of Public Works (PU) is continuing the construction of the Kemang Pratama Bridge in Bekasi, West Java, which sustained damage due to flooding in March 2025. Public Works Minister Dody Hanggodo has set a target for the completion of the bridge by August 2026.
“This bridge is being built to reduce travel time, lower vehicle operational costs, and improve safety and comfort for road users. The benefits must be directly felt by the community,” stated Dody, according to an official statement on Monday (01/06/2026).
The damage previously disrupted traffic flow in the South Bekasi area and its surroundings, affecting access to residential areas, economic hubs, and toll roads. Although the bridge is under the management of the Bekasi City Government, the reconstruction is being handled by the central government through the Jakarta-West Java National Road Implementation Office (BBPJN) under the Ministry of Public Works.
The Ministry of Public Works noted that as of 28 May 2026, the construction progress of the Kemang Pratama Bridge had reached 92.91%. This figure is higher than the planned target of 85.96%, representing a positive deviation of 6.95%. Meanwhile, the progress for the 2026 work year reached 92.06%, exceeding the target of 84.06% with a positive deviation of 7.97%.
Currently, work is focused on the final completion stages, including rigid pavement for the approach roads and asphalt finishing on the main span. The total length of the construction project is 410 metres with a bridge width of 7 metres. In addition to the main span, the work includes handling the approach roads on both sides of the bridge, specifically Approach A1 at 20 metres and Approach A2 at 230 metres.
The bridge construction is being carried out under a Multi-Year Contract (MYC) scheme for 300 calendar days, commencing on 31 October 2025, with completion targeted for August 2026. The Kemang Pratama Bridge serves as a vital access point connecting densely populated residential areas with the toll road network, including the Bekasi Barat and Jatiasih Toll Gates. Its existence is considered crucial for accelerating the movement of people and goods, while supporting economic activities in Bekasi and the surrounding regions.
Several traffic engineering measures have been implemented, including diverting vehicle flow from the Jatiasih and Galaxy directions towards Kemang Pratama via Jalan Ki Ijon Bin Beih towards Simpang PPI, regulating access to the Kemang Pratama Housing Estate through Gate 3 on Jalan Siliwangi, and diverting vehicles from the Pekayon direction towards Galaxy and Jatiasih via the Kemang Pratama Roundabout.
Source: jawawa.id (https://jawawa.id/newsitem/kemang-pratama-bridge-in-bekasi-expected-to-be-reopened-by-august-2026-1780871767)